Final | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Mark Moncarr
|
|
|
We need an electrical final for the gym, locker room area please. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok final Gym and cafeteria.
|
Electrical Rough-In | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Mark Moncarr
|
|
|
We need a ceiling cover inspection for the locker room corridor please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover locker room corridor S side of gym.
|
Final | 3/19/2019 | 3/20/2019 | 3/20/2019 | P | PART |
Mark Moncarr
|
|
|
We need a final inspection for the kitchen and commons areas please. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins Partial on kitch, and commons area. Construction still going on in gym and locker rooms. Signs to be placed on locked doors not allowing access to non-construction personnel.
|
Electrical Rough-In | 3/13/2019 | 3/14/2019 | 3/14/2019 | A | PASS |
Mark Moncarr
|
|
|
Kim Phone #: ###-#### Ok cover ceilings in kitch, vestibule, and space under mezzanine.
|
Electrical Rough-In | 2/14/2019 | 2/14/2019 | 2/14/2019 | A | PASS |
Mark Moncarr
|
|
|
We need a ceiling cover and wall cover inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover hard lid in bathroom areas NE corner, and short wall on W side to right before hallway entrance.
|
Electrical Rough-In | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Mark Moncarr
|
|
|
We need a cover inspection for the mezzanine area, dishwasher area, and restroom entry ceiling. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover S wall kitch, 2 cans outside bathrooms, and mezzanine.
|
Electrical Rough-In | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Mark Moncarr
|
|
|
We need a ceiling cover inspection for the locker rooms Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover ceilings in boys and girls locker rooms.
|
Permanent Service | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Mark Moncarr
|
|
|
We need a service inspection for the hillside junior high. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins p/s u/g n ok.
|
Conference | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | DONE |
Mark Moncarr
|
|
|
We need a consult for rough in for the gym area. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Discussed conduits runs below corrugated ceiling, clearances from.
|
Electrical Rough-In | 9/10/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Mark Moncarr
|
|
|
We need a masonary wall cover inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover outlets in kitchen area.
|
Electrical Rough-In | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | PASS |
Mark Moncarr
|
|
|
We need a block wall inspection. Please, thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover outside walls for N side locker rm, and E side janitors closet and storage.
|
Electrical Rough-In | 8/8/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Mark Moncarr
|
|
|
We would like a light pole base inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover light poles S side of school.
|
Electrical Rough-In | 8/8/2018 | 8/9/2018 | 8/9/2018 | P | PASS |
Mark Moncarr
|
|
|
We would like a light pole base inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover 3 lts. E side of front parking lot.
|
Electrical Rough-In | 8/7/2018 | 8/8/2018 | 8/8/2018 | P | PASS |
Mark Moncarr
|
|
|
We would like a light pole base inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover 3 lt poles E side.
|
Electrical Rough-In | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Mark Moncarr
|
|
|
We need an underground cover inspection on the east side of the project please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover 4-4" on secondary side of trans to new construction of school gym.
|
Electrical Rough-In | 8/3/2018 | 8/3/2018 | 8/3/2018 | A | PASS |
Mark Moncarr
|
|
|
Poles and pad Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover 4 li poles W side, and kitchen/cafeteria floor N side of school.
|
Electrical Rough-In | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | PASS |
Mark Moncarr
|
|
|
block and cover Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover grd work E side pole lights and E side gym floor. Conduit and masonary boxes installed in walls.
|
Electrical Rough-In | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Mark Moncarr
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover grd work for parking lot lights E and W side.
|
Electrical Rough-In | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PASS |
Mark Moncarr
|
|
|
We need a partial underground inspection please. Thank you, Kim. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover 1" for parking lot lights on S and W side of school.
|
Electrical Rough-In | 7/5/2018 | 7/5/2018 | 7/5/2018 | P | PASS |
Mark Moncarr
|
|
|
Ufer Ground Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover ufer E side of building.
|
Electrical Rough-In | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | CANC |
Mark Moncarr
|
|
|
We need a pole base inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Talked to electrical contractor. Tom Marshall with Public Works has done light pole inspection.
|