Final | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
James Ady
|
|
|
Matt Kirkland on site, ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins No signature sheet onsite final ok
|
Electrical Rough-In | 5/10/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling Grid Inspection Phone #: ###-#### Inspection requested via web by Bryan Atkins Boarders installed prior to inspection, not allowed. 3 small rooms grid rough in ok cover
|
Electrical Rough-In | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | PASS |
Tom Saunders
|
|
|
Call Matt on site if any questions, ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins... wall cover and hard lid locations ok to cover
|
Permanent Service | 4/5/2019 | 4/5/2019 | 4/5/2019 | A | PASS |
Tom Saunders
|
|
|
Call Matt on site if any questions, ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins... p/s u/g new ok...meter pack east side of building
|