Information based on query as of Sunday, June 2, 2024.
Permit Information
Permit NumberELE19-01628
StatusFinaled
Name POWERHOUSE ELECTRIC
Site Address 2909 W ELDER ST
Project Name 
Customer Number 
ePlanReviewNo
Description
New: New Hotel
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final3/19/20203/20/20203/20/2020PPASS
DetailsEric Story
Will be open, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
Occ card signed
Final ok
Final3/19/20203/20/20203/19/2020ACANC
DetailsEric Story
Will be open, thank you! Phone #: ###-#### >> Inspection requested via web by Darryn Coburn Inspection cancelled from web by: Darryn Coburn
Electrical Rough-In3/16/20203/16/20203/16/2020PPASS
DetailsEric Story
this request is for the 2nd floor, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
2nd floor hot checked in only rooms
Electrical Rough-In3/10/20203/11/20203/11/2020PPASS
DetailsEric Story
1st and 2nd floor corridor ceiling inspection at Airport hotel. Phone #: ###-#### Inspection requested via web by Darryn Coburn
1st and 2nd floor corridor ok to cover
*need cord removed above mini split in laundry areas as it is ran above ceiling
Final2/6/20202/7/20202/7/2020ACANC
DetailsEric Story
This request is for the 3rd floor, thank you!! Phone #: ###-#### Inspection requested via web by Darryn Coburn
No final at this time
Electrical Rough-In2/7/20202/7/20202/7/2020PPASS
DetailsEric Story
This request is for the 3rd floor, thank you!! Phone #: ###-#### Inspection requested via web by Darryn Coburn
3rd floor hot checked out
Final2/5/20202/6/20202/6/2020ACANC
DetailsEric Story
This request is for a final inspection for the 4th floor. Will be open, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
No final at this time
Electrical Rough-In2/6/20202/6/20202/6/2020PPASS
DetailsEric Story
This request is for a final inspection for the 4th floor. Will be open, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
4th floor hot checked-no furniture allowed as stated in a fowarded e-mail from fire marshall until fire supression system in operational
Final2/6/20202/7/20202/6/2020ACANC
DetailsEric Story
Will be open Phone #: ###-#### >> Inspection requested via web by Darryn Coburn Inspection cancelled from web by: Darryn Coburn
Electrical Rough-In1/29/20201/30/20201/30/2020APASS
DetailsEric Story
This request is for a ceiling inspection for level 3 and 4, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
3rd and 4th floor corridors suspended ceiling ok to cover
Electrical Rough-In1/21/20201/22/20201/22/2020PPASS
DetailsEric Story
this request is for a ceiling inspection for the first floor corridor, lobby and hallways. thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
1st floor hard lids in corridor and lobby area ok to cover
Electrical Rough-In1/3/20201/3/20201/3/2020PPASS
DetailsEric Story
This request is for the first floor ceiling cover for the dwelling units. Phone #: ###-#### Inspection requested via web by Darryn Coburn
1st floor units ceilings ok to cover@entry awning cans ok to cover
Electrical Rough-In11/27/201911/27/201911/27/2019PPASS
DetailsEric Story
This request is for the second floor corridor ceiling inspection, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
2nd Floor corridor hard lids only ok to cover
Electrical Rough-In11/18/201911/18/201911/18/2019PPASS
DetailsEric Story
This request is for an inspection of the 3rd floor corridor. Please call jerry with any questions ###-#### Phone #: ###-#### Inspection requested via web by Darryn Coburn
3rd floor hard lids in corridor ok to cover
Electrical Rough-In11/13/201911/13/201911/13/2019APASS
DetailsEric Story
Please inspect re-wiring of storage room ceiling on 4th Floor.
Jerry is on site. ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
4th floor storage room ceiling ok to cover
Permanent Service10/28/201910/28/201910/28/2019APASS
DetailsEric Story
Please inspect the main service Phone #: ###-#### Inspection requested via web by Darryn Coburn
AFC rating from IDPCO is 49,566 and main is 65K rated
p/s u/g n ok
Electrical Rough-In10/24/201910/25/201910/25/2019APASS
DetailsEric Story
This request is the the first floor rooms, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
First floor units ok to cover
Electrical Rough-In10/22/201910/22/201910/22/2019PPASS
DetailsEric Story
This request is for a pole base inspection, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
Light poles on west end ok to pour
Electrical Rough-In10/10/201910/11/201910/11/2019APASS
DetailsEric Story
4th floor units for rough-in
4th floor units ok to cover
Electrical Rough-In10/9/201910/10/201910/10/2019APASS
DetailsEric Story
The request is for the third floor rooms, thank you! Phone #: ###-#### Inspection requested via web by Darryn Coburn
3rd floor units ok to cover
Electrical Rough-In10/7/201910/8/201910/8/2019APASS
DetailsEric Story
Inspection is for the rough in for the electrical for 2nd floor rooms. Phone #: ###-#### Inspection requested via web by Darryn Coburn
2nd floor units ok to cover
Electrical Rough-In10/1/201910/1/201910/1/2019PPASS
DetailsEric Story
This request is for an underground inspection for the exterior front of the building. Please call Jerry with any questions ###-#### Phone #: ###-#### Inspection requested via web by Darryn Coburn
Front of building on elder ok to cover
Electrical Rough-In9/23/20199/23/20199/23/2019PPASS
DetailsEric Story
This request is for a partial rough/cover inspection for the common areas and stairwells, Please call Jerry with any questions he will be onsite, ###-#### Phone #: ###-#### Inspection requested via web by Darryn Coburn
Comm areas and stairways and halls throughout ok to cover(areas as noted will be one sided)
Electrical Rough-In9/5/20199/5/20199/5/2019PPASS
DetailsEric Story
This request is for a partial underground inspection Phone #: ###-#### Inspection requested via web by Darryn Coburn
U/G on west side and middle ok to cover
east still yet to be done at this time
Electrical Rough-In8/26/20198/26/20198/26/2019PPASS
DetailsEric Story
This request is the an underground inspection in parking lot, please meet Jerry in parking lot. Thank you!! Phone #: ###-#### Inspection requested via web by Darryn Coburn
Parking lot and secondaries/inside lobby area were sheetrocking ceiling proir to drop ceiling ok to cover
Electrical Rough-In5/15/20195/16/20195/16/2019APASS
DetailsEric Story
This request is for floor outlets in the northwest corner of the slab. Thank You! Phone #: ###-#### Inspection requested via web by Darryn Coburn
Floor boxes ok to cover
Electrical Rough-In5/3/20195/6/20195/6/2019APASS
DetailsEric Story
this request is for an underground inspection please Phone #: ###-#### Inspection requested via web by Darryn Coburn
U/G for inside building all power and data ok to cover