General Inspection | 3/15/2018 | 3/15/2018 | 3/15/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 11/8/2017 | 11/9/2017 | 11/9/2017 | A | PASS |
Michael Zawacki
|
|
|
Deweatering complete. Site contained. Hoping to have paving crew in on 11-17.
|
General Inspection | 8/22/2017 | 8/23/2017 | 8/24/2017 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/24/2017 | 8/24/2017 | 8/24/2017 | A | PEND |
Andy J. Long
|
|
|
Dewatering in progress. Using frack tank for sediment treatment. Water still has visible turbidity and is discharging into large onsite private stormwater system. No discharge discovered to retention/drainage pond that receives water per ACHD storm drain maps.
No plumes or discharges discovered in Gallagher Canal nor downstream from Drain 3 in Loggers Creek.
Investigation in progress. Iron Horse and McAlvain will continue to monitor water quality.
|
Site Preparation | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PEND |
Andy J. Long
|
|
|
discuss dewatering plan and ESC plan @ 9
Plan is to dewater to a 18,000 gallon frack tank that will then gravity discharge into the existing storm drain vault in Albertson's parking lot. The center's stormwater discharges to the DD3 pond south of the center.
Treatment through frac tank should be adequate, but will verify quality with turbidity test samples at frac tank outlet.
|