Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberESC17-00936
StatusFinaled
Name PAT PALMER
Site Address 3022 S OWYHEE ST
Project NameOwyhee Park Aprtments
Customer Number 
ePlanReviewNo
Description
2 acre site, 3 apartment buildings within project area. This permit covers total project area of disturbance, (includes grading and site work and one building). Other two buildings permitted separately. CGP 2017 tracking # IDR12BA60. Protect MS4 inlets on Pasadena and Owyhee. Construction entrance and permit sign to be posted on Owyhee. Set up staging area to satisfy pollution prevention requirements. ESC site preparation inspection is required
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final11/6/201811/8/201811/9/2018PPASS
DetailsMichael Zawacki
General Inspection11/5/201811/5/201811/6/2018 CANC
DetailsAndy J. Long
rescheduled for site fInal
Site Final9/20/20189/20/20189/20/2018PNR
DetailsAndy J. Long
Mud in gutter on Pasadena Street needs to be cleaned up ASAP.

Verbarl correction request to RP Jeremy. Follow up scheduled for next week. Storm drain has sediment protection, dry conditions. No other violations.

Need to remove DI bag on Pasedena after cleanup and landscaping is complete.
General Inspection9/17/20189/17/20189/17/2018 FAIL
DetailsMichael Zawacki
Lots of mud in gutter on Pasadena. Paint washout has been thrown on dirt and sidewalk.
About half of landscaping complete.
General Inspection7/31/20187/31/20188/1/2018 PASS
DetailsMichael Zawacki
All buildings are framed and work is on interior. Interior parking lot is paved and gutters conpleted. Some sections of sidewalk along Owyhee need repair. Some loose trash in site, some areas of sidewalk are covered with dirt and pit run.
General Inspection6/14/20186/14/20186/14/2018PPASS
DetailsMichael Zawacki
WIP on vertical and interiors. Site has had parking lot paved, no workers driving on exposed dirt. Curbing complete around perimeter, most sidewalks done. Site is free from trash.
Random Inspection5/18/20185/18/20185/18/2018PPASS
DetailsMichael Zawacki
Curb and gutter now complete, site is contained. Lumber scraps will soon need to be picked up. SWPPP doesn't have an inspection since 4-9
General Inspection5/2/20185/2/20185/2/2018PPEND
DetailsMichael Zawacki
Some building material on site that needs to be cleaned and disposed. Currently working on framing and installing curbing on perimeter.
Syman SWPPP reports don't seem to be meeting the 14 day set in SWPPP or are not being put in completed inspection section. Rainfall triggered inspections completed, if changing to monthly and rain triggered SWPPP needs to be updated.
General Inspection3/20/20183/20/20183/20/2018PPEND
DetailsMichael Zawacki
Two exits and neither are stabalized. Some trackout, called RP Jeremy and asked for repairs and cleaning. Rest of site is contained and clean, trash was being removed while I was on site.