Site Final | 10/11/2018 | 10/11/2018 | 10/11/2018 | P | PASS |
Andy J. Long
|
|
|
Building complete and occupied. Landscaping and stabilization is in progress, site stormwater system is operational and retains water on site.
See ESC17-01200 for Gowen Industrial Park main site permit for remaining work and monitoring of stabilization and vegetation.
|
General Inspection | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Michael Zawacki
|
|
|
Exterior complete. Work on grading and prep for paving. Water truck on site, no dust.
|
Random Inspection | 6/25/2018 | 6/25/2018 | 6/25/2018 | A | PASS |
Andy J. Long
|
|
|
Gowen Industrial park buildings and site improvements are in progress.
SWPPP and Boise ESC permit sign posted on Eisenman and Beechcraft. No trackout from site entrances, concrete washout facility located on site. MS4 stormdrains have sediment protection.
No corrections requested. See also ESC17-01200
|
General Inspection | 5/24/2018 | 5/24/2018 | 5/24/2018 | P | PASS |
Michael Zawacki
|
|
|
Entire site inspection. WIP on 3 tilt ups. Curbing is about half complete, site is free from dust and loose trash. Concrete washout is almost full. Some light trackout.
|
General Inspection | 5/10/2018 | 5/10/2018 | 5/10/2018 | P | PASS |
Michael Zawacki
|
|
|
Shells of two tilt ups complete and working on cores. WIP on construction of third tilt up. Site is prepped for curb, paving supposed to be in a month. Water truck on site, very little dust for size of site. Entrance and curbs are being installed off of Eisenman.
|
General Inspection | 3/27/2018 | 3/27/2018 | 3/27/2018 | P | PASS |
Michael Zawacki
|
|
|
Large site, 2 buildings up and work on 3rd pad. Inspect all together. Washout is clean and maintained, no trackout or other issues. Site is mostly below grade and no dirt is leaving site. Worker parking area is pit run and not muddy, only one way in or out. Lots of water currently on site, dust is not an issue. Machines in mud are not leaving site.
|