General Inspection | 12/3/2018 | 12/12/2018 | 12/12/2018 | P | CANC |
Andy J. Long
|
|
|
|
Site Final | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 12/3/2018 | 12/3/2018 | 12/3/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Michael Zawacki
|
|
|
Exterior of building and most of parking lot work complete. Area still need to be landscaped. Bare area are belo grade of sidewalk.
|
General Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 | | PASS |
Michael Zawacki
|
|
|
Entire area is below grade of parking lot. Dumpster on site, area clean and trash free.
|
General Inspection | 7/26/2018 | 7/26/2018 | 7/27/2018 | | PASS |
Andy J. Long
|
|
|
WIP progress on earthwork for landscaping. Building shell and parking lot are complete. Crew using hose to water down stockpile that is being moved. Approved.
|
Site Preparation | 6/5/2018 | 6/5/2018 | 6/5/2018 | P | PART |
Michael Zawacki
|
|
|
Adam Phone #: ###-#### Site is below grade of parking lot. Will need stabalized entrance, already has trackout leaving site. Water will be needed for dust control. Concrete washout needed, old dumped washout was exposed on site during prep.
|