General Inspection | 12/19/2018 | 12/19/2018 | 12/19/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 12/19/2018 | 12/19/2018 | 12/19/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 12/4/2018 | 12/4/2018 | 12/4/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/19/2018 | 11/19/2018 | 11/19/2018 | | PASS |
Andy J. Long
|
|
|
Parking lot asphalt and pavers are installed. WIP placing topsoil and landscaping around parking lot. No violations observed.
|
General Inspection | 10/30/2018 | 11/1/2018 | 11/5/2018 | P | PASS |
Michael Zawacki
|
|
|
Sent message to RP to remove silt fence.
|
General Inspection | 10/30/2018 | 10/30/2018 | 10/30/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/15/2018 | 10/15/2018 | 10/15/2018 | | PART |
Michael Zawacki
|
|
|
Silt fence still along canal and is falling apart. Chainlink fence installed between parking lot and silt fence, fence installers tracked lots of dirt into lot.
|
General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 | | PASS |
Michael Zawacki
|
|
|
No new activity since last inspection.
|
General Inspection | 9/13/2018 | 9/13/2018 | 9/17/2018 | | PASS |
Michael Zawacki
|
|
|
Parking lot completed. Area still needs to be landscaped. Silt fence still protecting canal.
|
General Inspection | 8/29/2018 | 8/29/2018 | 8/29/2018 | | PASS |
Michael Zawacki
|
|
|
Parking lot, curbs and sidewalk completed. Perimeter still needs to be landscaped, topsoil pile is on site. Silt fence installed along canal, torn in one spot.
|
General Inspection | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | PASS |
Michael Zawacki
|
|
|
Parking lot paved and porous pavers installed. Crew on site working on sidewalk, curb, and gutters. Eco pan washout on site and used. Silt fence still installed along canal, can use some maintenance.
|
General Inspection | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Michael Zawacki
|
|
|
Curb is installed. BMPs still on site and maintained. SWPPP is still being inspected and reports are in book. SWPPP & permit sign has been tipped over.
|
General Inspection | 3/7/2018 | 3/8/2018 | 3/9/2018 | P | PASS |
Andy J. Long
|
|
|
No activity on parking lot. No trackout or runoff from site.
|
General Inspection | 1/3/2018 | 1/3/2018 | 1/3/2018 | P | PASS |
Michael Zawacki
|
|
|
Site frozen, no dirtwork. Siltfence installed, SWPPP on site, no issues.
|
Random Inspection | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | PASS |
Michael Zawacki
|
|
|
No track out leaving site.
|
Site Preparation | 12/6/2017 | 12/6/2017 | 12/6/2017 | A | PASS |
Michael Zawacki
|
|
|
Jason 11:00 AM 12/6 Met with contractor. BMPs in place. Only concern now is track out while hauling away material.
|