General Inspection | 5/31/2019 | 5/31/2019 | 5/31/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Michael Zawacki
|
|
|
Please refer to ESC17-01754
|
General Inspection | 4/15/2019 | 4/15/2019 | 4/15/2019 | | FAIL |
Andy J. Long
|
|
|
No construction entrance. Lots of workers and delivery services driving through mud and puddles on site. Trackout. Washing concrete washwater into the ground
Corrections: - Install construction entrance - install lined washout facility. Post washout sign - sweep Hudson, Targee, and Federal Way SE bound.
SEE ESC17-01754 for follow up inspections
|
General Inspection | 2/27/2019 | 2/27/2019 | 2/27/2019 | | PASS |
Michael Zawacki
|
|
|
Inspected 2-26. Site was contained and free of trackout at time of inspection.
|
General Inspection | 1/8/2019 | 1/8/2019 | 1/8/2019 | | FAIL |
Andy J. Long
|
|
|
Ongoing trackout issues. See ESC17-01754 for inspection reports and enforcement
|
General Inspection | 11/21/2018 | 11/21/2018 | 11/21/2018 | | PART |
Michael Zawacki
|
|
|
Inside site is clean and organized. Issue comes from entrance being compacted river rocks and workers parking on bare shoulder of road. Street is currently clean. Parking will become problem once ground starts becoming wet and muddy. Multiple warnings have been given about concerns.
|
General Inspection | 10/5/2018 | 10/5/2018 | 10/5/2018 | | CANC |
Andy J. Long
|
|
|
see ESC17-01754
|