Aging Inspection | 2/12/2020 | 2/12/2020 | 2/12/2020 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 2/12/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Michael Zawacki
|
|
|
|
Aging Inspection | 12/11/2019 | 12/11/2019 | 12/11/2019 | | PASS |
Michael Zawacki
|
|
|
Site is clean and contained. Exterior looks completed, no activity.
|
Aging Inspection | 10/9/2019 | 10/9/2019 | 10/9/2019 | | PASS |
Michael Zawacki
|
|
|
Material covered, lot contained, no esc issues.
|
Aging Inspection | 8/9/2019 | 8/9/2019 | 8/9/2019 | | PASS |
Michael Zawacki
|
|
|
Lot bare and contained. No esc issues.
|
General Inspection | 11/28/2018 | 11/29/2018 | 11/29/2018 | P | PASS |
Michael Zawacki
|
|
|
Lot is bare and flat. No stockpiles or storage on site. Roofers currently working. nSidewalks are clean, no dirt leaving site.
|
BMP Violation | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Andy J. Long
|
|
|
follow up
Stockpile now has a perimeter wattle to capture sediment runoff. DI bag installed on storm drain. Approved.
|
BMP Violation | 9/26/2018 | 9/27/2018 | 9/27/2018 | P | PEND |
Andy J. Long
|
|
|
GC called to say that they will install sediment protection on storm drain, remove excess dirt and then install perimeter protection as needed.
Compliance extended to 9/28 PM
|
Random Inspection | 9/26/2018 | 9/26/2018 | 9/26/2018 | P | FAIL |
Andy J. Long
|
|
|
WIP on excavating new basement under exisiting historic home. Large stockpiles onsite with no perimeter sediment control. Storm drain directly in front site does not have inlet sediment protection.
Verbal corrections request to remodel contractor to return call for ESC conference
|