Permit Information
Permit NumberESC19-00289
StatusIssued
Name JOEL HIRTLE
Site Address 10060 W SMOKE RANCH DR
Project NameUnion Square #4
Customer Number 
ePlanReviewNo
Description
Heavy duty >= 50 ft construction entrance required. Protect existing storm drains on Smoke Ranch. Water truck or water tower must be on site to control fugitive dust during construction. Provide leakproof concrete washout and covered trash containment. Site preparation inspection is required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection6/30/20206/30/20207/1/2020 PASS
DetailsAndy J. Long
All units complete on Smoke Ranch and Campville. DI bags stilled installed. Lined washout located at Bent Rock. Will need a new one when units on Bent Rock begin.

No ESC violations observed
Aging Inspection4/28/20204/28/20204/28/2020 PASS
DetailsMichael Zawacki
Landscapers on site doing sprinklers for almost every home. Lined concrete washout on site. Only vacant lots are the ones the furthest west.
All home exterior work is completed.
Landscapers need to sweep when work completed.
BMP Violation2/24/20202/27/20202/27/2020APASS
DetailsMichael Zawacki
Washout cleaned, large washout on site. SOme dirt on roads from excavator crew on site at time of inspection.
Lined washout should have some rock installed in front of it, small gap between washout and sidewalk.
General Inspection2/24/20202/24/20202/24/2020PFAIL
DetailsMichael Zawacki
Site is dirty, dumped washout, tracking on streets and sidewalk. Notified Colby, he is listed as RP ut not on site. Fine issued, follow up scheduled.
General Inspection1/15/20201/15/20201/15/2020 PASS
DetailsMichael Zawacki
All lots along north perimeter have homes framed. All trash clean. Lots are frozen, no tracking.
General Inspection11/15/201911/15/201911/15/2019PPASS
DetailsMichael Zawacki
No construction activity, no staging or storing of equipment, no ground disturbances.
Inlet protection installed and lots surveyed.
General Inspection10/22/201910/22/201910/22/2019PPASS
DetailsAndy J. Long
Subdivision infrastructure installed and complete. Lots are prepped for construction. Storm drains in sub have been fitted with DI bags. No muddy runoff or issues observed. Will keep open for when new SFHs begin. Approved.
Site Preparation4/16/20194/16/20194/17/2019PPASS
DetailsAndy J. Long
MS4 inlets have sediment protection installed. Permit sign posted. Excavation/earth work to begin shortly when ground has dried out enough.

Crew is too install heavy duty rock construction entrance. Approved for construction and staging. Follow up scheduled.