General Inspection | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Michael Zawacki
|
|
|
Noo workers on site. Sidewalks and curb work has begun. Two washouts on site, nonen dumped on ground. Road be in place, no paving. Lots of bare area.
|
General Inspection | 6/5/2020 | 6/8/2020 | 6/9/2020 | P | PASS |
Michael Zawacki
|
|
|
No new activity at site, starting to overgrow
|
Aging Inspection | 6/5/2020 | 6/5/2020 | 6/5/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/3/2020 | 3/17/2020 | 3/23/2020 | P | FAIL |
Andy J. Long
|
|
|
No activity at site. No trackout or discharges from site. No wind blown dust observed at time of inspection.
Site is out of compliance for stabilzation deadlines. Incactive disturbed area and stockpiles with no temporary statbilization.
|
General Inspection | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PART |
Andy J. Long
|
|
|
No activity, no trackout. Dry conditions. No wind blown dust observed at time of construciton.
Corrections needed: - updated construction schedule - stabilize stockpile or become active. Beyond stockpile stabilization deadline - install new construction entrance prior to resuming grading activity
Notified RP John. He will provide updates and schedule on corrections.
Follow up inspection scheduled
|
General Inspection | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | PASS |
Michael Zawacki
|
|
|
Site utility prep work is completed. No workers on site. Area is all bare, large stockpile at site.
|
Tracking Control | 12/6/2019 | 12/9/2019 | 12/10/2019 | P | PASS |
Michael Zawacki
|
|
|
Talked to foreman while at site. Had entrance rerocked yesterday. Not expecting any deliveries or anyone coming to site. Area is clean, no dirt leaving perimeter.
|
General Inspection | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | FAIL |
Andy J. Long
|
|
|
No construction entrance or stabilized area for workers. Some trackout onto Victory.
Notified RP to have SCE installed, follow up scheduled.
|
General Inspection | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Michael Zawacki
|
|
|
Site is rough graded. East side below grade of neighboring lot, west iha silt fence, small section damaged, looks like game trail going over it, no dirt breached. WIP on sewer, victory is closed, work in street and parcel. Water truck on site, fuel and maintenace vehicle also on site, one person doing fueling.
|
General Inspection | 10/8/2019 | 10/8/2019 | 10/9/2019 | P | CANC |
Michael Zawacki
|
|
|
|
Site Preparation | 8/29/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Andy J. Long
|
|
|
w/ John RP
Silt fence perimeter on down gradient site border and irrigation ditch has been properly installed. SWPPP permit posted. Construction to begin next week or following week, will post City of boise ESC permit sign and install heavy duty construction entrance.
|