General Inspection | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PASS |
Michael Zawacki
|
|
|
One section of sidewalk has forms, not yet poured. Washout on site and in use. Road has been patched.
|
BMP Violation | 4/8/2020 | 4/15/2020 | 4/15/2020 | A | PASS |
Michael Zawacki
|
|
|
Dasco on site doing trenching. Dumped washout is gone.
|
General Inspection | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | FAIL |
Michael Zawacki
|
|
|
Washout pan on site, not used. Picture sent toRP, follow up scheduled.
|
General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Michael Zawacki
|
|
|
Trenching for sewer taps is done. CXrew on site, looks like they are doing fill for seepage beds. No trackout.
|
General Inspection | 2/10/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Michael Zawacki
|
|
|
Well point in place, not currently pumping. No standing water or issues from yesterdays dewatering. Will continue to monitor until sewer is completed. Sewer inspector keeps us informed if issues arise.
|
Site Preparation | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Andy J. Long
|
|
|
Site prep requested by Kade with Capital Paving.
WIP on sewer connection. Small volume of trench dewatering being contained on site. Construction entrance installed. Crews parking on the pavement. No ESC requests at this time.
Approved.
|