INSP-Final Inspection | 10/17/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Jake Adams (BSD) will be on site with copy of plans. We finally have a clean FACP! Please call Jake 30 minutes prior to Inspector arrival. Phone #: ###-#### Inspection requested via web by Jeff Gooch
|
INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 | P | FAIL |
Troy Cobbley
|
|
|
No approved plans or small documents available. No inspection for this permit performed.
Jeff Gooch will be on site with thumb drive of plans Phone #: ###-#### Inspection requested via web by Jeff Gooch
|
INSP-Final Inspection | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | FAIL |
Mark Scharfen
|
|
|
No stamped prints on site. 3 troubles on fire alarm panel. 1-Missing SLC card (attic devices). 1 dirty smoke and 1 NAC battery troulbe. Told school that troubles will need to be clear and stamped prints on site for next test.
The fire doors in the main hallway for A, B, C wing, and cafeteria are repaired and latch closed when released from magnetic door holder. The Auditorium concession roll up door is now repaired. This should apply to FIR13-00187 as well, FIR17-00400 was pulled to address FIR13-00187 for some reason. Phone #: ###-#### Inspection requested via web by Jeff Gooch
|
INSP-Conference | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | NR |
Troy Cobbley
|
|
|
Jeff and I spoke about the items needed to final this permit. It appears that a FIR issued in 2017 was to address some of these items. Jeff is going to follow up.
###-####
|
INSP-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | NR |
Troy Cobbley
|
|
|
I spoke to jeff about the items needed for this inspection. He is going to follow up on the door status for the original 2013 FIR permit
Original permit issued in 2017, District unsure of what actions, if any, took place. Door closures in Auditorium are the subject of this permit. Please inspect and advise if corrections are necessary. Phone #: ###-#### Inspection requested via web by Jeff Gooch
|