INSP-Final Inspection | 2/1/2019 | 2/4/2019 | 2/4/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | FAIL |
Jim Page
|
|
|
Add fire sprinkler in coridor next to kitchen on top level as discussed.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | CANC |
Jim Page
|
|
|
Inspection will need to be rescheduled due to time constraints.
After nine o’clock please Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overehad fire sprinkler piping complete. Overhead fire sprinkler located between conditioned spaces approved for cover. Overhead fire sprinkler piping located in attic spaces or below unconditioned spaces cannot be covered until a tenting inspection is complete. Any cover that is installed before tenting inspection will be removed to verify tenting is in place.
Need a rough to cover on the 1st and second floors so they can insulate. We will have you back out for a second rough in inspection for the attic piping tenting prior to sheet rock Phone #: ###-#### Inspection requested via web by Sam Ball
|