Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberFIR18-00617
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 8000 S FEDERAL WAY
Project NameMicron - B36 Cafeteria Remodel
Customer Number 
ePlanReviewYes
Description
Owner is renovating an existing servery area as well as installing new walk in coolers and freezers. Viking is to update the existing fire sprinkler system to conform to the new wall and ceiling layout per NFPA13, 2016. This project includes demo of all sprinkler heads in affected area and new installation of new heads to match existing. Also to include installing 11 dry pendant sprinkler heads in the coolers and freezers. This permit includes work on the 1" drops only. The underground, riser, cross mains, and branch lines are all existing and are to remain as is.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/11/20191/14/20191/14/2019PPASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.

POC is Zack Grasmick Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in1/10/20191/11/20191/11/2019PPASS
DetailsTroy Cobbley
See the city approved plans for piping above the lay-in ceiling that is ok for cover. One pendant needs to be added at the column as marked on the plans.


Rough to cover inspection for the servery area of this project. Foreman on job is Zack Grasmick Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in/Hydro1/11/20191/14/20191/11/2019PCANC
DetailsJim Page
Hydro test to be perfromed same time as permit FIR18-00382. POC is Zack Grasmick Phone #: ###-#### >> Inspection requested via web by Brett Lawatch Inspection cancelled from web by: Brett Lawatch
INSP-Sprinkler Rough-in11/14/201811/15/201811/15/2018PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above grid in area of work complete, approved for cover.

Rough in inspection of 2nd half of Kitchen/Server area. Zack Grasmick is foreman on job. Phone #: ###-#### Inspection requested via web by Brett Lawatch
INSP-Sprinkler Rough-in11/5/201811/5/201811/5/2018PPASS
DetailsTroy Cobbley
See the city approved plans for piping marked "ok" that can be covered in the Kitchen area.

Rough to Cover inspection for Phase 2. Foreman is Zack Grasmick Phone #: ###-#### Inspection requested via web by Brett Lawatch