Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberFIR18-00813
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2033 S HUDSON AVE
Project NameSkyline Bldg G UG
Customer NumberUDG ONLY
ePlanReviewYes
Description
[Skyline Building G - UDG Only] - Quick Permit
Install a 2" CPVC fire line into the new Apartment Bldg.

[BLD17-04628]
Building G: (SKYLINE APARTMENTS – BUILDING TYPE 2, Building A, B, C, E, G and J) (24 units)PLAN MOD RELOCATE WAHER/DRYER FROM BATHROOM TO HALLWAY ADD CLOSED DOOR AS NOTED ON APPROVED PLANS 7-2-18**AJS**The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 25,320 square foot three story VB Type of Construction apartment building (8,458 sq. ft. 1st story and 8,431 sq. ft. 2nd story and 8,431 sq. ft. 3rd story). Each unit is 1 story. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, 1-hr dwelling unit separations, 1 hour fire barriers for stair and breezeways, rated doors in breezeway, interior nonbearing walls, millwork, and finishes. Special Inspection is NOT required. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R as regulated by the Fire Department. Separate fire sprinkler permits shall be obtained prior to beginning any modification or installation work on such systems. **ajs**192 unit apartment project with (9) apartment buildings, clubhouse, and associated site work
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/1/201910/2/201910/2/2019PPASS
DetailsJim Page
Final inspection for underground supply complete.

Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection9/12/20199/17/20199/16/2019PCANC
DetailsJim Page
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro4/29/20194/30/20194/30/2019PDONE
DetailsTroy Cobbley
Underground hydro witnessed with 4psi loss on guage which is acceptable per NFPA 13

Gerardo Phone #: ###-####
INSP-Supply line flush4/26/20194/29/20194/29/2019PPASS
DetailsMark Scharfen
04/29-Conducted flush with suez. Passed.

Gerardo Arce is the contact for this flush inspection. Stacey with Suez told us he is available in the PM. Could we get a call in advance so we can notify a time for Stacey to come? Thank you for your help. Have a good day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush4/9/20194/11/20194/11/2019AFAIL
DetailsJim Page
Underground valve could not be found.

Gerardo Arce is the contact. Stacy from Suez has this on his schedule, contact him for a more specific time. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush11/8/201811/13/201811/13/2018PCANC
DetailsTroy Cobbley
Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro11/8/201811/13/201811/13/2018PFAIL
DetailsTroy Cobbley
Piping was not holding minimum starting pressure

Phone #: ###-#### Inspection requested via web by Stan Beus