INSP-Final Inspection | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
Contact Noemi Carrero ###-#### 30 min prior to UG Final Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | DONE |
Jim Page
|
|
|
Underground hydrostatic test witnessed, no pressure loss observed.
Contact Tyler Loomis ###-#### 30 min prior to Hydro insp start please.
Thx Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Supply line flush | 4/25/2019 | 4/25/2019 | 4/25/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
INSP-Sprinkler Rough-in | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover. noted that the underground supply was not routed the same as what the print showed due to valve location froim SUEZ, an as built will be required for submittal before final inspection to verify that the correct waterflow will work with the new pipe route, if figures do not work then corrections to the install will be required.
Contact Hunter Anderson ###-#### 30 min Prior to UG RTC insp start please, he would like to do this after 1 or 2 PM today if possible.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 11/27/2018 | 11/28/2018 | 11/27/2018 | A | CANC |
Jim Page
|
|
|
Contact Hunter Anderson ###-#### 30 min Prior to RTC Insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|