INSP-Final Inspection | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test witnessed with no loss on the guage
Gabe Garduno is the contact. This is for a hydro only, in connection with the flush scheduled for the same day and time. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush witnessed.
|
INSP-Sprinkler Rough-in | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for undergorund supply complete, approved for cover.
Call Jim Page to verify he witnessed pipe installation back in 2018. Shilo contact is Brian Collins. Thank you for everything you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|