INSP-Final Inspection | 6/12/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | FAIL |
Troy Cobbley
|
|
|
Plan mod needed for changing the hallway strobes to 30cd, need to show Mezzanine and Mechanical Room notification devices, need to test Gym duct smoke detectors and change two devices to weather proof. Need to witness notification testing.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | PART |
Troy Cobbley
|
|
|
Phase 1 fire alarm complete. See comments by Lee for items needing correcting from the Phase 1 inspection prior to a final fire alarm permit sign off.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 3/20/2019 | 3/21/2019 | 3/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
Not all of the plan package on site, drawings (facp, amp not same as drawings) no dialer shown, smoke over facp too low. No testing performed.
Partial Final for cafeteria and commons. Dirk is Contact. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|