INSP-Final Inspection | 8/7/2019 | 8/8/2019 | 8/8/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Mike O Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in/Hydro | 7/26/2019 | 7/26/2019 | 7/26/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for newly installed piping witnessed, no pressure loss observed.
Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | DONE |
Jim Page
|
|
|
24 hour air test has been witnessed, no pressure loss observed.
24 hour air test. Mike Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping in area of work complete.
Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/14/2019 | 6/17/2019 | 6/17/2019 | A | PART |
Jim Page
|
|
|
Inspection for pre-set hangers complete.
Hanger Attachments Rick Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|