Final | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Jack Reynolds
|
|
|
Inspector aware of situation and is communicating with Tyrel Inspection requested via web by Arielle Hendricks - 5lb flue pressure test -gas piping size for furnace ok
|
Final | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | FAIL |
Jack Reynolds
|
|
|
Larren ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks - need to prove 1/2" gas line is big enough for furnace - need to flue test
|
Final | 11/19/2018 | 11/21/2018 | 11/21/2018 | P | CANC |
Jack Reynolds
|
|
|
Please call on way: Tyrel ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks-
|
Pressure Test | 11/19/2018 | 11/21/2018 | 11/21/2018 | P | CANC |
Jack Reynolds
|
|
|
Please call on way: Tyrel ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks- not sure what needed to be pressure tested on this site
|
Pressure Test | 11/19/2018 | 11/20/2018 | 11/19/2018 | P | CANC |
Jack Reynolds
|
|
|
Please call on way: Tyrel ###-#### Phone #: ###-#### >> Inspection requested via web by Arielle Hendricks Inspection cancelled from web by: Arielle Hendricks
|
Rough-in | 10/3/2018 | 10/9/2018 | 10/9/2018 | A | PASS |
Jack Reynolds
|
|
|
Please call the customer when on way: Larren Novak ###-#### We had a partial pass on the last Rough-In because we needed a Blast and Flue Test. The Blast has been done, the Flue Test will be ready when we FINAL the job. Phone #: ###-#### Inspection requested via web by Krista Boss- duct blast ok- still need to prove 1/2" gas line is big enough for the furnace- flue test will be done at final- will want to see dryer vent box sealed at final
|
Rough-in | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PART |
Troy James
|
|
|
Would like early PM and call on way. Phone #: ###-#### Inspection requested via web by Xanti Berria ok to cover new addition only, need duct blast test, flue test and prove the 1/2" to furnace is big enough, need test to flue
|
Pressure Test | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | CANC |
Jack Reynolds
|
|
|
Would like early PM and call on way Phone #: ###-#### >> Inspection requested via web by Xanti Berria Inspection cancelled from web by: Xanti Berria
|
Final | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | CANC |
Jack Reynolds
|
|
|
Would like early PM Phone #: ###-#### >> Inspection requested via web by Xanti Berria Inspection cancelled from web by: Xanti Berria
|
Rough-in | 7/13/2018 | 7/16/2018 | 7/16/2018 | A | PART |
Jack Reynolds
|
|
|
Please call on way: Larren ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- man J ok- supply ducting in crawl space ok- return ducting in attic ok-
|
Rough-in | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | CANC |
Jack Reynolds
|
|
|
Late PM. We are fixing this today in the afternoon, so please call before arrival: Gener ###-#### Phone #: ###-#### >> Inspection requested via web by Krista Boss Inspection cancelled from web by: Krista Boss
|
Rough-in | 7/9/2018 | 7/10/2018 | 7/9/2018 | A | CANC |
Jack Reynolds
|
|
|
Phone #: ###-#### >> Inspection requested via web by Krista Boss Inspection cancelled from web by: Krista Boss
|
Rough-in | 7/9/2018 | 7/9/2018 | 7/9/2018 | P | FAIL |
Jack Reynolds
|
|
|
Please call on way: Darrius ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- flex ducting is being smash by floor joistes- need to have an approved Man J.
|
Rough-in | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | CANC |
Jack Reynolds
|
|
|
ok to pour concrete - please call Brett ###-#### Phone #: ###-#### >> Inspection requested via web by Krista Boss Inspection cancelled from web by: Krista Boss
|