INSP-Final | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | DONE |
Troy Cobbley
|
|
|
Permit finaled. Call Alicia when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
DOC - Permit Finaled | | | 4/24/2020 | | DONE |
|
|
|
per troy c
|
INSP-Sprinkler Rough-in/Hydro | 9/15/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Troy Cobbley
|
|
|
**Hydro and tenting passed * MAS**
Hydro and tenting needed, rough passed last week. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2019 | 9/13/2019 | 9/13/2019 | P | PART |
Jim Page
|
|
|
Hydro was not ready, rough in inspection complete, piping between conditioned spaces approved for cover, not all tenting in place at time of inspection, cover is not approved where tenting is required.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2019 | 9/12/2019 | 9/12/2019 | P | FAIL |
Jim Page
|
|
|
Sprinkler head/heads at top of stairs do not extend past wall as shown on approved drawings.
Call Anthony before heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|