Case Summary (BLD) | | | 3/4/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Third Notice | | 2/7/2015 | 2/17/2015 | | DONE |
|
|
|
This permit finaled on the web by Cecyle Brock
|
Second Notice | | 1/12/2015 | 2/2/2015 | | DONE |
|
|
|
|
First Notice | | 12/20/2014 | 1/2/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/10/2014 | | DONE |
|
|
|
|
BLD-Final | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | PASS |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
BLD-Final | 11/12/2014 | 11/12/2014 | 11/13/2014 | P | PART |
Dave Hannah
|
|
|
Mark Phone #: ###-#### ok for temp occ need elec to go perm and finish ada rest room
|
FIRE-Final Inspection | 11/10/2014 | 11/12/2014 | 11/12/2014 | A | PASS |
Forrest France
|
|
|
Life safety inspection passed provided approved style hardware is installed at the south exit door- removed keyed lock deadbolt at this location prior to structural final.
|
BLD-Conference | 11/5/2014 | 11/5/2014 | 11/5/2014 | P | DONE |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 9/25/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Dave Hannah
|
|
|
please call 15 min before for access// mark Phone #: ###-####
|
BLD-Framing/Rough-in | 9/25/2014 | 9/25/2014 | 9/25/2014 | P | CANC |
Dave Hannah
|
|
|
Mark Phone #: ###-####-please call 15 minutes prior for access
|
Override - Parcel Holds | | | 9/17/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 9/17/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 9/17/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 9/17/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 8/13/2014 | 8/13/2014 | 9/15/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 9/9 DowntownLevel 3 TI - ePlanReview - Henriksen Butler
|
Routing - PLAN CHECK | 9/15/2014 | | 9/15/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/13/2014 | | 9/9/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 9/9/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 8/13/2014 | 8/13/2014 | 8/19/2014 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - Addressing | 8/13/2014 | | 8/14/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/13/2014 | | 8/13/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 8/13/2014 | | 8/13/2014 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - Exterior entry change Applicant has the zoning certificate in progress for exterior changes to the building. Interior TI is good for approval.
|
Routing PW Sewer Rating | 8/13/2014 | | 8/13/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Pending Assignment by JCB | 8/13/2014 | | 8/13/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 8/12/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard and plan review fees paid.
|
Application received | | | 8/11/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 11 2014 2:34PM
|