Third Notice | | 7/14/2015 | 7/27/2015 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
Second Notice | | 6/20/2015 | 7/9/2015 | | DONE |
|
|
|
mailed 7-10-15
|
First Notice | | 6/6/2015 | 6/10/2015 | | DONE |
|
|
|
Mailed out 6-10-15
|
Permanent Occupancy | | | 5/27/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/30/2015 | 5/1/2015 | 5/1/2015 | P | PASS |
Dave Hannah
|
|
|
Ron// both floors Phone #: ###-####
|
FIRE-Final Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Katie Marron
|
|
|
Fire life safety pass
|
FIRE-Final Inspection | 4/16/2015 | 4/17/2015 | 4/17/2015 | A | PART |
Katie Marron
|
|
|
Fire Lifesafety pass for 2nd floor. Final pending finishes at first floor.
|
BLD-Ceiling Grid Inspection | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Dave Hannah
|
|
|
Ron Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/26/2015 | 3/27/2015 | 3/27/2015 | A | PART |
Dave Hannah
|
|
|
Ron Phone #: ###-#### ok to install boarder tiles
|
BLD-Framing/Rough-in | 2/20/2015 | 2/23/2015 | 2/24/2015 | A | PASS |
Dave Hannah
|
|
|
Ron Phone #: ###-####
|
BLD-Framing/Rough-in | 2/9/2015 | 2/10/2015 | 2/10/2015 | A | PART |
Dave Hannah
|
|
|
Ron Phone #: ###-#### second floor ok to cover
|
Permit Ready to Issue | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
(F) Reprint permit | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue PAID IN FULL permit | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 12/19/2014 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 11/19/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2014 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 10/28/2014 | | 11/19/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 10/28/2014 | | 11/19/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 10/28/2014 | 10/28/2014 | 11/4/2014 | | PASS |
Scott Arellano
|
|
|
Attached Fire Code comments to plans. Plans approved with red lined comments.
|
Routing - Addressing | 10/28/2014 | | 10/28/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/28/2014 | | 10/28/2014 | | PASS |
Beverly Mountain
|
|
|
|
Telephone call | | | 10/27/2014 | | DONE |
|
|
|
Adrienne Lane-Martin called and asked me to delete all her electrical plans in eplan review. She said she uploaded the wrong plans. I deleted the electrical plans she uploaded and uploaded the electrical sheets she emailed to me. KRS
|
Intake Approval | | | 10/27/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 10/23/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 23 2014 10:04AM
|