Permit Information
Permit NumberBLD18-04369
StatusFinaled
Name THE RUSSELL CORPORATION
Site Address 592 N BENJAMIN LN
Project NameAmherst Madison Office TI
Customer NumberEPLAN BLD18-04243
ePlanReviewNo
Description
**TWO PERMITS IN EPLAN UNDER BLD18-04243** (AMHERST MADISON REAL ESTATE OFFICE TI) (CUP18-00014) (DRH18-00061) // 01/02/20 PLAN MOD TO ENLARGE 2ND FLR RESTROOMS, ADD OFFICE DOORS. JAR // Permit to establish occupancy for a new 11,014 sq ft office tenant space in a new 2-story office building constructed under BLD18-04243. Work to include: interior non-bearing partition walls, doors and interior relites; electrical, plumbing, and mechanical; and interior finishes in compliance with Ch. 8 of the 2015 IBC. Two-way communication is required at the elevator landing in accordance with 2015 IBC 1009.8. All work shall comply with the approved plans, and all applicable codes. This building is NOT Fire Sprinklered. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/19/20207/28/2020 DONE
This permit finaled on the web by Caloub Huttash
First Notice 5/22/20207/9/2020 DONE
mailed 7-9-2020
Telephone call  5/12/2020 DONE
Confirmed with Jared from the Russel Corporation that ELE19-03525 was for both the TI and the Shell/Core.
Permanent Occupancy  5/12/2020 DONE
BLD-Final5/11/20205/11/20205/11/2020PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Jared Waggoner. Ok for perm occ.
Zoning Approval5/11/20205/11/20205/11/2020 PASS
DetailsKatelyn Menuge
BLD-Conference5/6/20205/6/20205/6/2020PDONE
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Final5/4/20205/4/20205/4/2020PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Jared Waggoner
FIRE-Final Inspection5/4/20205/4/20205/4/2020APASS
DetailsTroy Cobbley
Life safety passed.

Phone #: ###-#### Inspection requested via web by Jared Waggoner
FIRE-Final Inspection4/29/20204/30/20204/30/2020PFAIL
DetailsTroy Cobbley
Permit can be finaled when the project related fire alarm permit and the Grading permit have been finaled. Jared Phone #: ###-####
BLD-Ceiling Grid Inspection3/25/20203/26/20203/26/2020PPASS
DetailsMike Jordan
2nd floor 3 west offices for ceiling cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Ceiling Grid Inspection3/20/20203/20/20203/20/2020PPART
DetailsMike Jordan
2nd floor ceiling grid for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner. Grid ok pending electrical and mech. rough in inspection.
BLD-Ceiling Grid Inspection3/16/20203/17/20203/17/2020PPASS
DetailsMike Jordan
First floor ceiling grid Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Framing/Rough-in3/4/20203/4/20203/4/2020PPASS
DetailsMike Jordan
2nd floor cloud ceiling framing for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Wall Bracing2/17/20202/18/20202/18/2020AFAIL
DetailsMike Jordan
Ist floor west exterior wall interior shear Phone #: ###-#### Inspection requested via web by Jared Waggoner. Engineer of record to provide alternate attachment details for areas that are inaccessable to provide attachments.
BLD-Framing/Rough-in2/12/20202/13/20202/13/2020APASS
DetailsMike Jordan
First floor suspended GWB ceiling and 2 exterior canopies for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Wall Bracing2/10/20202/11/20202/11/2020APASS
DetailsMike Jordan
2nd floor east interior shear wall Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Energy code compliance2/10/20202/10/20202/10/2020APASS
DetailsMike Jordan
2nd floor E/W/S exterior wall insulation Phone #: ###-#### Inspection requested via web by Jared Waggoner. Remainder of 2nd floor exterior walls ok.
BLD-Energy code compliance2/7/20202/7/20202/7/2020PPASS
DetailsMike Jordan
Foreman Phone #: ###-####. North exterior wall only ok.
Override - Parcel Holds2/7/20201/1/19002/7/2020  
Per Bob A. override
BLD-Framing/Rough-in2/6/20202/6/20202/6/2020PPASS
DetailsMike Jordan
2nd floor walls and ceilings for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Framing/Rough-in2/3/20202/3/20202/3/2020PPART
DetailsTony Young
Framing inspection for 1 side at interior 2nd floor walls Phone #: ###-#### Inspection requested via web by Jared Waggoner/// ok to one side from 10' up pending trades
BLD-Energy code compliance1/23/20201/24/20201/24/2020APASS
DetailsJim Storey
First floor wall insulation Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Framing/Rough-in1/22/20201/22/20201/22/2020PPASS
DetailsMike Jordan
First floor rough framing for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner. 1st. floor i nterior steel stud framed walls ok. hardlids ok pending mech. rough in inspection.
BLD-Wall Bracing1/13/20201/13/20201/13/2020PPASS
DetailsMike Jordan
90% exterior sheet metal shear inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner
Print Occupancy Form  1/6/2020 DONE
CHANGE STATUS TO (ISS)  1/6/2020 DONE
Plan assigned to (JAR)12/20/201912/20/20191/2/2020 DONE
DetailsJulie Romig
12/27 (5 days) - Plan Mod Amherst Madison
Routing - PLAN CHECK12/23/2019 1/2/2020 PASS
DetailsJulie Romig
Permit Ready to Issue  1/2/2020 DONE
**DO NOT REISSUE - PLAN MOD: IN EPLAN BLD18-04243
Routing - PLUMBING12/23/2019 12/27/2019 PASS
DetailsDan Ediger
Plan Mod approved per Dan Ediger in ePlanReview
Routing - MECHANICAL12/23/2019 12/23/2019 PASS
DetailsTroy James
Plan Mods
Plan Modification Accepted  12/20/2019 DONE
Enlarge 2nd floor restrooms, add three interoffice doors, revise phone booth lights. (All electrical sheets are being resubmitted as the previous engineer left the firm.)
BLD-Concrete11/14/201911/15/201911/15/2019APART
DetailsMike Jordan
2nd floor slab on deck reinforcement Phone #: ###-#### Inspection requested via web by Jared Waggoner. 2nd. floor slab on deck. work in progress. Needs to install perimeter #4 bar and splice 15ft. at re-enterant corners. Special inspection to verify.
BLD-Other11/4/201911/4/201911/4/2019PDEFR
DetailsMike Jordan
8" CMU grout at east patio walls at 2:30 pm 12''-16'', will have special inspection. Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Other10/31/201911/1/201911/1/2019PPEND
DetailsMike Jordan
CMU grout from 8''-12'' at 1pm, will have special inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner. PEnding special inspection.
BLD-Other10/30/201910/31/201910/31/2019PPART
DetailsMike Jordan
4''-8'' CMU grout at 3pm, will have special inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner. 4ft. to 8ft. elevation for CMU wall at patio.
BLD-Other10/30/201910/31/201910/31/2019ADEFR
DetailsMike Jordan
0-4'' CMU grout at 10am, will have special inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner
Print Occupancy Form  10/21/2019 DONE
BLD-Concrete10/16/201910/17/201910/17/2019PPASS
DetailsMike Jordan
Slab on Grade Reinforcement Phone #: ###-#### Inspection requested via web by Jared Waggoner
BLD-Foundation9/27/20199/27/20199/27/2019PPASS
DetailsBrandon Shaw
Ok to place concrete pending special inspection.
BLD-Footing9/18/20199/18/20199/18/2019PPART
DetailsMike Jordan
Call 30 minutes ahead // Jerrod Phone #: ###-####. Perimeter footings, column pad footings, interior footings and elevator and trash enclosure footings. Noted clearance issues in some areas. Special inspection agency to verify clearane issues have been repaired prior to conc. placement. Ok to place concrete pending special inspection.
Issue PAID IN FULL permit  9/18/2019 DONE
Plan assigned to (JAR)8/13/20198/13/20199/17/2019 DONE
DetailsJulie Romig
1st Rev Comp - 4th Comp - Amherst Madision TI
Permit Ready to Issue  9/17/2019 DONE
please do not issue without BLD18-04243
Routing - PLAN CHECK9/10/2019 9/17/2019 PASS
DetailsJulie Romig
5th Review
Routing - PLUMBING9/11/2019 9/11/2019 PASS
DetailsJulie Romig
Passed per ePlanReview and BLD18-04243
Routing - PLAN CHECK8/22/2019 9/9/2019 FAIL
DetailsJulie Romig
4th Review
Routing Off Site - STRUCTURAL8/22/2019 9/4/2019 PASS
DetailsJulie Romig
AHJ - 3rd Review
Routing - PUBLIC WORKS8/22/2019 8/23/2019 PASS
DetailsJulie Romig
Passed per ePlanReview and BLD18-04243
Routing - PLUMBING8/22/2019 8/22/2019 FAIL
DetailsJulie Romig
failed per ePlanReview
Plan resubmittals received  8/13/2019  
resubmittal per Julie Romig
Extend Review Timeline  5/24/2019 DONE
1st approved 180 day extension per adele. see documents
Telephone call  5/15/2019 DONE
Marla Carson requested an extension, forward emailed to Adele.
Routing - Erosion and Sediment12/5/2018 5/7/2019 PASS
DetailsAndy J. Long
See ESC18-01466. Project already has ESC coverage. VOID
Routing - PLUMBING4/1/2019 4/20/2019 PASS
DetailsDaryl Spivey
1) provide tempered water to lavs as required by ISPC 407.3
2) Provide secondary roof drainage as required
Plan assigned to (JAR)12/5/201812/5/20184/19/2019 DONE
DetailsJulie Romig
1st Rev Comp - 2nd Comp - 502 Amherst Madison Office TI
Routing - Design Review4/1/2019 4/19/2019 PASS
DetailsKatelyn Menuge
Redlined Changes
PLANS/APPL TAKEN TO FRONT DESK  4/19/2019 DONE
Permit Ready to Issue  4/19/2019 DONE
still need ACHD-NEED
ACHD
REVISED VALUE-met
GC FORM-met
Routing - PLAN CHECK4/1/2019 4/18/2019 FAIL
DetailsJulie Romig
Routing - FIRE4/1/20194/1/20194/5/2019 PASS
DetailsErika Akin
Attached revised comments to case
Routing - MECHANICAL4/1/2019 4/3/2019 PASS
DetailsTroy James
Routing - PUBLIC WORKS4/1/2019 4/2/2019 PASS
DetailsAngela Hardy
WBSD
Routing Off Site - STRUCTURAL4/1/2019 4/1/2019 PASS
DetailsJulie Romig
Route to Impact Fee Review1/10/20191/13/20191/10/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  1/9/2019 FAIL
DetailsJulie Romig
Routing - PLAN CHECK12/5/2018 1/9/2019 FAIL
DetailsJulie Romig
Routing - FIRE12/5/201812/5/20181/2/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing Off Site - STRUCTURAL12/5/2018 12/17/2018 FAIL
DetailsJulie Romig
Routing - MECHANICAL12/5/2018 12/13/2018 PASS
DetailsTroy James
Intake Approval  12/13/2018 PASS
DetailsJulie Romig
Intake approval date of TI application submittal. Reviewed under shell/core permit BLD18-04243 in ePlan.
Routing - Design Review12/5/2018 12/5/2018 FAIL
DetailsKatelyn Menuge
See BLD18-04243
Routing - PLUMBING12/5/2018 12/5/2018 PASS
DetailsDaryl Spivey
1) provide tempered water to lavs as required by ISPC 407.3
2) Provide secondary roof drainage as required by ISPC.
Routing - Addressing12/5/2018 12/5/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/5/2018 12/5/2018 PASS
DetailsMorgan Webb
Application received 12/5/2018   
Application received 12/5/2018