BLD-Final | 2/21/2020 | 2/25/2020 | 2/25/2020 | A | PASS |
Tony Young
|
|
|
call ahead // PJ Phone #: ###-####
|
DOC - Permit Finaled | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 2/20/2020 | 2/21/2020 | 2/21/2020 | P | DEFR |
Tony Young
|
|
|
call ahead // PJ Phone #: ###-####,, will be completed next week for saftey coverings
|
BLD-Final | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PART |
Tony Young
|
|
|
call ahead // PJ Phone #: ###-####/// ok after finishing the saftey glass covering within 24"of the doors
|
BLD-Blower Door Test Results | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | DONE |
Tony Young
|
|
|
Call: PJ Smith on way to inspection. PJ Would like to walk through home with inspector, 208 559 0588
Have a great weekend!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith/// 3.5
|
BLD-Final | 2/14/2020 | 2/19/2020 | 2/19/2020 | A | NR |
Tony Young
|
|
|
Call: PJ Smith on way to inspection. PJ Would like to walk through home with inspector, 208 559 0588
Have a great weekend!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Blower Door Test Results | 2/14/2020 | 2/19/2020 | 2/19/2020 | A | NR |
Tony Young
|
|
|
Call: PJ Smith on way to inspection. PJ Would like to walk through home with inspector, 208 559 0588
Have a great weekend!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Final | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | NR |
Tony Young
|
|
|
Call: PJ Smith on way to inspection. PJ Would like to walk through home with inspector, 208 559 0588
Have a great weekend!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith// needs tempered glass,, blower door test results,, fire caulk,, landing,,
|
PubWorks Occupancy Approval | 2/7/2020 | 2/7/2020 | 2/7/2020 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Other | 10/29/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Tony Young
|
|
|
Please have inspector call PJ Smith (Builder) before heading to inspection
Thank you- PJ Smith 208 559 0588 Phone #: ###-#### Inspection requested via web by PJ Smith// soffits work in progress,, ok
|
BLD-Energy code compliance | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Tony Young
|
|
|
Please have inspector call PJ Smith (Builder) before heading to inspection
Thank you- PJ Smith 208 559 0588 Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Framing/Rough-in | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Brandon Shaw
|
|
|
PJ Phone #: ###-####
|
Routing - MECHANICAL | 10/10/2019 | | 10/10/2019 | | PASS |
Troy James
|
|
|
Revised manual j report
|
BLD-Foundation | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | PASS |
Tony Young
|
|
|
Plans will be at job site. PJ Smith is out of town please call Tyler 208 906 9050 for questions. Hey Tony..... Drew Deer tag in unit 45..... only 10 tags Thats 50 days from now- Catch ya next week Have a great week.... PJ Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Footing | 6/19/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Tony Young
|
|
|
Call PJ Smith 208 559 0588 4332 N Eyrei Way Boise ID 83703 Have a great weekend! Elk season is 72 days Phone #: ###-#### Inspection requested via web by PJ Smith
|
PubWorks Subgrade Approval | 6/18/2019 | 6/18/2019 | 6/18/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 5/6/2019 | | DONE |
|
|
|
|
Telephone call | | | 1/30/2019 | | DONE |
|
|
|
Left voicemail for PJ to inform him the permit is ready and what fees are due.
|
OVERRIDE | | | 1/29/2019 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/29/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/29/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/29/2019 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 1/15/2019 | | 1/29/2019 | | DONE |
Michael Hanson
|
|
|
01/28 #404 L2 Paper
|
Routing - FIRE | 1/25/2019 | 1/15/2019 | 1/28/2019 | | PASS |
Lee G Meredith
|
|
|
New SFH paper
2000 gpm for 90 minutes allowed by Ron Johnson. No sprinklers required.
|
Routing - PLAN CHECK | 1/15/2019 | | 1/28/2019 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 1/28/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - Erosion and Sediment | 1/24/2019 | | 1/25/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified stormwater team designated. Site preparation inspection is required.
|
Routing - MECHANICAL | 1/23/2019 | | 1/24/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/23/2019 | | 1/23/2019 | | PASS |
Brent Moore
|
|
|
|
Routing - PUBLIC WORKS | | | 1/23/2019 | | PASS |
|
|
|
|
Routing PW Grading-Hillside | 1/23/2019 | | 1/23/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
|
Route to Impact Fee Review | 1/16/2019 | 1/19/2019 | 1/17/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 1/15/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/15/2019 | | PASS |
|
|
|
|
Routing - Addressing | 1/15/2019 | | 1/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/2/2019 | | DONE |
|
|
|
|
Application received | | 12/19/2018 | | | |
|
|
|
|