Second Notice | | 7/19/2020 | 7/21/2020 | | DONE |
|
|
|
This permit finaled on the web by Mike Burden
|
First Notice | | 5/21/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Permanent Occupancy | | | 5/11/2020 | | DONE |
|
|
|
|
BLD-Final | 5/4/2020 | 5/5/2020 | 5/5/2020 | P | PASS |
Jim Storey
|
|
|
screened // Jay Phone #: ###-####
|
FIRE-Final Inspection | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Jim Page
|
|
|
Fire alarm inspection is complete, no fire sprinklers, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work is complete, signatures provided on permit sign off card.
screened // Jay Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/7/2020 | 4/8/2020 | 4/8/2020 | A | PASS |
Tell Riley
|
|
|
*screened* - Jay Phone #: ###-####//music room grid ok//
|
BLD-Framing/Rough-in | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PASS |
Jim Storey
|
|
|
Jay Phone #: ###-#### ada aproch
|
BLD-Foundation | 4/18/2019 | 4/19/2019 | 4/19/2019 | P | PASS |
Jim Storey
|
|
|
Jay Phone #: ###-#### rebar ok pending si.
|
BLD-Footing | 4/12/2019 | 4/15/2019 | 4/15/2019 | P | PART |
Jim Storey
|
|
|
Jay Phone #: ###-#### all west si pending// rfi for r10 insulation under slab..
|
Issue PAID IN FULL permit | | | 4/8/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/8/2019 | | DONE |
|
|
|
|
Telephone call | | | 4/5/2019 | | DONE |
|
|
|
Tried to get ahold of Mike Burden with Scott Hedrick Construction to get an email to send the permits over. Office message states the office is closed today.
|
Plan assigned to (JAR) | 1/2/2019 | 1/3/2019 | 1/28/2019 | | DONE |
Julie Romig
|
|
|
02/01 - 3rd Rev - 1st Rev Comp - 502 Hawthorne Elementary Music Classroom Remodel
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/28/2019 | | DONE |
|
|
|
MET
NEED
REVISED VALUE
MET
***USE STATE FEES FOR SCHOOLS (OVER PAID CAUSE VALUE WENT DOWN AT LATER DATE- MATH INVOLVED)***
NEED
met-GC FORM
|
Routing - PLAN CHECK | 1/23/2019 | | 1/23/2019 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 1/23/2019 | | 1/23/2019 | | PASS |
Julie Romig
|
|
|
|
Route to Impact Fee Review | 1/16/2019 | 1/19/2019 | 1/17/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - MECHANICAL | 1/3/2019 | | 1/17/2019 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 1/3/2019 | | 1/17/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 1/3/2019 | | 1/16/2019 | | PASS |
Daryl Spivey
|
|
|
Per plans and ISPC
|
Routing - FIRE | 1/2/2019 | 1/3/2019 | 1/15/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 1/15/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - ELECTRICAL | 1/3/2019 | | 1/15/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 1/3/2019 | | 1/15/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 1/3/2019 | | 1/10/2019 | | FAIL |
Julie Romig
|
|
|
AHJ - Corrections Required per ePlanReview
|
Application received | | | 1/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 7 2019 5:02PM
|
Intake Approval | | | 1/2/2019 | | PASS |
Joe Bruce
|
|
|
|