Print Statement | | | 8/13/2020 | | DONE |
|
|
|
2ND PAST DUE
|
Print Statement | | | 7/22/2020 | | DONE |
|
|
|
1st mailed statement
|
Second Notice | | 5/17/2020 | 6/3/2020 | | DONE |
|
|
|
This permit finaled on the web by Kaki Sam
|
First Notice | | 4/19/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020
|
Permanent Occupancy | | | 4/9/2020 | | DONE |
|
|
|
|
Zoning Approval | 4/8/2020 | 4/8/2020 | 4/8/2020 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Final | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PASS |
Dave Hannah
|
|
|
*Screened* - Jim Phone #: ###-#### ok after zoning finals
|
FIRE-Final Inspection | 3/27/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Jim Phone #: ###-####
|
BLD-Final | 1/9/2020 | 1/10/2020 | 1/10/2020 | A | PART |
Jim Storey
|
|
|
leonard Phone #: ###-#### final ok pending fire/zonning for perm.
|
FIRE-Final Inspection | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PART |
Jim Page
|
|
|
Per conversation with Troy Cobbley, 90 Day TCO authorized by Ron Johnson with Boise Fire, signature provided on permit card for 90 day TCO.
Lenor Phone #: ###-####
|
PubWorks Occupancy Approval | 1/8/2020 | 1/8/2020 | 1/8/2020 | | DONE |
Tiffany Lowery
|
|
|
|
Elevation Cert Rec'd-Final | | | 1/7/2020 | | DONE |
|
|
|
Public Works has recieved the final Elevation Certificate. Jason Taylor
|
Routing PW Flood Plain | 1/7/2020 | | 1/7/2020 | | PASS |
Jason C. Taylor
|
|
|
Recieved final EC.
|
Zoning Approval Temp | 1/3/2020 | 1/3/2020 | 1/3/2020 | | PASS |
Katelyn Menuge
|
|
|
Temp BND20-00001
|
BLD-Conference | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | DONE |
Brandon Shaw
|
|
|
pre-final walk-through // Leonard Phone #: ###-####
|
Plan Reviewer's activity | | | 12/20/2019 | | DONE |
Joe Bruce
|
|
|
Spoke with architect about updating plans to show a 1-hour rated fire riser room and removing the tanks that are shown on the drawings. Revised sheet A101 and had it batch stamped for field inspection.
|
FIRE-Final Inspection | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide city approved plans and small docuements, provide above ground tank as per review notes #5, #6 and #7, the impact protection for the tank does not appear to meet IFC 312, provide building and elevator keys for knox box, provide fire dept. access per review note #15. The above items and not all inclusive due to no plans and notes available. Other items may be noted at next inspection.
Lenard Phone #: ###-####
|
BLD-Framing/Rough-in | 9/25/2019 | 9/25/2019 | 9/25/2019 | A | PASS |
Jim Storey
|
|
|
2nd floor and lobby
|
BLD-Framing/Rough-in | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Jim Storey
|
|
|
first floor ok
|
CHANGE STATUS TO (ISS) | | | 9/12/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (JHB) | 9/4/2019 | 9/4/2019 | 9/10/2019 | | PASS |
Joe Bruce
|
|
|
09/13 plan mod - Knife River, ePlan
|
Routing - PLAN CHECK | 9/6/2019 | | 9/10/2019 | | PASS |
Joe Bruce
|
|
|
|
Permit Ready to Issue | | | 9/10/2019 | | DONE |
|
|
|
plan mod so do not re issue-
need rev cert of val for the plan mod-
|
BLD-Framing/Rough-in | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PASS |
Jim Storey
|
|
|
fire treated ply
|
Plan Modification Accepted | | | 9/4/2019 | | DONE |
|
|
|
plan mod #1
|
BLD-Concrete | 8/1/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Jim Storey
|
|
|
Inspection for slab on metal deck Phone #: ###-#### Inspection requested via web by leonard loewen
|
BLD-Concrete | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | PASS |
Jim Storey
|
|
|
Inspect reinforcement on slab on grade Phone #: ###-#### Inspection requested via web by leonard loewen
|
Elevation Cert Rec'd-Midconst | | | 7/18/2019 | | DONE |
|
|
|
Recieved EC #2, ok for framing. JCT
|
Issue PAID IN FULL permit | | | 5/23/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/23/2019 | | DONE |
|
|
|
|
Telephone call | | | 4/10/2019 | | DONE |
|
|
|
GC submitted new value for this project. The new value refects the building of the new building minus the foundation work on BLD19-01109.
|
Meeting | | | 4/8/2019 | | DONE |
|
|
|
sent email to kiki informing fee amount due and that a letter from ACHD is still required for issuance as well
|
Permit Ready to Issue | | | 4/5/2019 | | DONE |
|
|
|
MET-fees paid but still need ACHD-
NEED-
ACHD
Met
GC form
Revised Vlaue (kikis@mcalvain.com)
|
Plan assigned to (JHB) | 2/7/2019 | 2/7/2019 | 4/4/2019 | | PASS |
Joe Bruce
|
|
|
04/05 (3rd Rev) 03/12 - 502 Knife River Office/Repair Bldg (Fire)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2019 | | DONE |
|
|
|
|
Routing - FIRE | 4/1/2019 | 4/1/2019 | 4/3/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Final Review 04.03.2019.pdf uploaded.
|
Plan resubmittals received | | | 4/1/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - FIRE | 3/21/2019 | 3/21/2019 | 3/27/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 2nd review 03.27.2019.pdf uploaded and emailed to architecht.
|
Plan resubmittals requested | | | 3/27/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 3/21/2019 | | 3/26/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 3/21/2019 | | 3/25/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing - Design Review | 3/21/2019 | | 3/22/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 3/22/2019 | | DONE |
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
Routing PW Flood Plain | 3/21/2019 | | 3/22/2019 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
Plan resubmittals received | | | 3/21/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing PW Drainage | 3/21/2019 | | 3/21/2019 | | PASS |
Brian Murphy
|
|
|
approved grading permit
|
Route to Impact Fee Review | 3/12/2019 | 3/15/2019 | 3/15/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/30/2019 | 2/7/2019 | 3/12/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 03.12.2019.pdf uploaded and emailed to architecht.
|
1st review completed | | | 3/12/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 3/12/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 2/7/2019 | | 3/11/2019 | | FAIL |
Joe Bruce
|
|
|
Emailed plan review report to architect. **JHB**
|
Routing Off Site - STRUCTURAL | 2/7/2019 | | 2/21/2019 | | FAIL |
Joe Bruce
|
|
|
KPFF
|
Routing PW Drainage | 2/7/2019 | | 2/21/2019 | | FAIL |
|
|
|
need siw form drainage report o and m report detail sheet
|
Routing - PLANNING | 2/7/2019 | | 2/14/2019 | | PASS |
David Moser
|
|
|
|
Routing PW Flood Plain | 2/7/2019 | | 2/14/2019 | | FAIL |
Jason C. Taylor
|
|
|
Upload Elevation Certificates. Elevation Certificate elevations need to be placed on site plan, foundation plan, and cross section plans. Jason Taylor ###-####
|
Routing PW Environmental | 2/7/2019 | | 2/13/2019 | | PASS |
Rick Christenson
|
|
|
No drains shown in shop area. Flammable Exterior Interceptor needed if floor drains are added in repair shop area.
|
Routing - MECHANICAL | 2/7/2019 | | 2/11/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 2/7/2019 | | 2/8/2019 | | FAIL |
Katelyn Menuge
|
|
|
Minimum front setback before curb/paving can begin is seven feet.
Please upload the landscape plan.
|
Routing - Addressing | 2/7/2019 | | 2/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Street Lights | 2/7/2019 | | 2/8/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 2/7/2019 | | 2/7/2019 | | PASS |
DeAnn Brown
|
|
|
Sewer connection approved in GRD18-00092
|
Routing - PUBLIC WORKS | 2/7/2019 | | 2/7/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 2/7/2019 | | 2/7/2019 | | PASS |
Michael Zawacki
|
|
|
VOID. Please refer to ESC18-01761
|
Routing - PLUMBING | 2/7/2019 | | 2/7/2019 | | PASS |
Daryl Spivey
|
|
|
See redline remarks. Install per plan and ISPC.
|
Routing PW Solid Waste | 2/7/2019 | | 2/7/2019 | | PASS |
Evan Carpenter
|
|
|
|
Plan Reviewer's activity | | | 1/30/2019 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 1/30/2019 | | PASS |
Carl Westfall
|
|
|
Prescreen approved by CJW and fees paid 1/30/19
|
Intake Approval | | | 1/16/2019 | | FAIL |
|
|
|
(1-16-19) Refer to the circled items in the Plan Intake Checklist. Resolve each item as directed. CJW
|
Intake Approval | | | 1/16/2019 | | FAIL |
|
|
|
(1-16-19) Refer to last unresolved circled items in the Plan Intake Checklist. Resolve that item as directed. CJW
|
Application received | | | 1/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 9 2019 12:41PM
|