Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD19-00314
StatusFinaled
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 2158 E SUMMERSWEET DR
Project NameFalcon One Storage Condos #3
Customer NumberBLD18-04070-04076,19-00314-00317
ePlanReviewYes
Description
(FALCON ONE STORAGE CONDOS) (BUILDING # 3) (12 PERMITS FILED UNDER BLD18-03877) Permit is for Building #1B that totals 7,533 SF with (8) eight storage units. There is a total of 8 storage building areas located on a single parcel. The entire scope of work includes construction of 12 individual storage buildings with a total of 107 storage units, a 658 sq. ft. clubhouse space with two single user restrooms, and a small counter with a sink. These buildings are not fire sprinklered. The buildings are divided into fire areas that shall not exceed 12,000 sq. ft. Special inspections required per attached Form 310. Approval is contingent upon adhering to the approved plans on file and attached engineering. **JHB**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 7/20/20208/11/2020 DONE
MAILED 8-14-2020
Permanent Occupancy  7/10/2020 DONE
BLD-Final7/8/20207/9/20207/9/2020APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by chad stradley
BLD-Aging Inspection7/6/20207/6/20207/8/2020 PASS
DetailsJim Storey
Change Expiration Date Only  5/21/2020 DONE
BLD-Aging Inspection5/4/20205/4/20205/4/2020 PASS
DetailsJim Storey
Zoning Approval4/28/20204/28/20204/28/2020 PASS
DetailsKatelyn Menuge
Change Expiration Date Only  4/24/2020 DONE
TCO extended per Jason Blais. See DOCs
Telephone call  4/23/2020 DONE
Emailed Jerod Pogue at Wright Brothers to let him know his TCO will expire soon and to request an extension from Jason Blais
Telephone call  3/26/2020 DONE
emailed GC TCO courtesy letter. See docs.
BLD-Aging Inspection3/3/20203/3/20203/3/2020 PASS
DetailsJim Storey
Change Expiration Date Only  1/22/2020 DONE
permit extension per Jason Blais - see DOCS
Telephone call  1/22/2020 DONE
request for extension approved by Jason Blais. 90 days. See DOCS
BLD-Framing/Rough-in1/2/20201/3/20201/3/2020APASS
DetailsJim Storey
Fire Barrier inspection. Phone #: ###-#### Inspection requested via web by chad stradley gyp ok/fire stopping ok
1st review completed  12/12/2019 FAIL
DetailsJoe Bruce
Temporary Occupancy11/21/20192/19/202011/21/2019 DONE
DetailsGemma Flores
Plan Reviewer's activity  11/20/2019 DONE
DetailsJoe Bruce
Mechanical and Plumbing inspection NOT REQUIRED on this permit per discussion with Chad at Wright Brothers. **JHB**
BLD-Final11/18/201911/19/201911/19/2019PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by chad stradley final ok pending others for perm
BLD-Final11/18/201911/19/201911/19/2019ANR
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by chad stradley
FIRE-Final Inspection11/18/201911/19/201911/19/2019PPASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for this scope of work complete, signature provided on permit sign off card.

Phone #: ###-#### Inspection requested via web by chad stradley
PubWorks Occupancy Approval10/25/201910/25/201910/25/2019 DONE
DetailsTiffany Lowery
BLD-Framing/Rough-in10/22/201910/23/201910/23/2019APASS
DetailsJim Storey
Late am for fire wall inspection. Insulators will be installing wool fire batting in the am. Thank you. Phone #: ###-#### Inspection requested via web by chad stradley
Zoning Approval Temp10/18/201910/18/201910/18/2019 DONE
DetailsKatelyn Menuge
BND19-00190
BLD-Framing/Rough-in10/8/201910/10/201910/11/2019PPART
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by chad stradley finsh framing on firewall to exterior/ all other atras ok to cover.
BLD-Conference9/24/20199/25/20199/25/2019APASS
DetailsJim Storey
Exterior fire barrier inspection on building. Phone #: ###-#### Inspection requested via web by chad stradley gyp and screws ok
BLD-Footing7/30/20198/1/20198/1/2019APASS
DetailsJim Storey
rebar inspection for footer Phone #: ###-#### Inspection requested via web by chad stradley
BLD-Footing7/30/20197/31/20197/31/2019PPASS
DetailsJim Storey
Footer rebar inspection . After 3pm would be preferable. They are setting bar in the morning. Thank you Phone #: ###-#### Inspection requested via web by chad stradley si on site rebar ok.
Change Expiration Date Only  7/17/2019 DONE
permit reissued by mistake on 7/16/19
Print Occupancy Form  7/16/2019 DONE
CHANGE STATUS TO (ISS)  7/16/2019 DONE
Permit Ready to Issue  7/15/2019 DONE
DO NOT REISSUE - PLAN MOD
Plan assigned to (JHB)6/27/20196/27/20197/12/2019 PASS
DetailsJoe Bruce
(plan mod) Falcon One, Bldg 1B
Routing Off Site - STRUCTURAL7/11/2019 7/12/2019 PASS
DetailsJoe Bruce
Plan resubmittals received  7/11/2019 DONE
DetailsJoe Bruce
Plan resubmittals requested  7/8/2019 DONE
DetailsJoe Bruce
Emailed structural comments to architect.
Routing - PLAN CHECK6/27/2019 7/8/2019 PASS
DetailsJoe Bruce
Routing Off Site - STRUCTURAL6/27/2019 7/3/2019 FAIL
DetailsJoe Bruce
Plan Modification Accepted  6/27/2019 DONE
Plan mod accepted in e plan-changing footing & framing design -assigned to Joe B-Candy missed putting in with the others
Plan Modification Accepted  6/13/2019 DONE
Plan mod accepted in e plan-changing footing & framing design -assigned to Joe B
Permit Ready to Issue  2/13/2019 DONE
Need
Revised Value- (for each building)

(DO NOT ISSUE WITHOUT ALL PERMITS, BLD18-03877, BLD18-04070 TO BLD18-04076, BLD19-00314 TO BLD19-000317)
Issue PAID IN FULL permit  2/13/2019 DONE
Print Occupancy Form  2/13/2019 DONE
CHANGE ISSUED DATE  2/13/2019 DONE
permit reissued by mistake on 7/16/19
Plan assigned to (JHB)11/14/201811/14/20182/11/2019 PASS
DetailsJoe Bruce
(3rd Rev Comp) 12/07 - (502) Falcon One Storage Condos Bldg 1(B)
Routing Off Site - STRUCTURAL2/8/2019 2/11/2019 PASS
DetailsJoe Bruce
PLANS/APPL TAKEN TO FRONT DESK  2/11/2019 DONE
Plan resubmittals received  2/8/2019 DONE
DetailsJoe Bruce
Plan resubmittals requested  2/6/2019 FAIL
DetailsJoe Bruce
Structural resubmittal required.
Routing Off Site - STRUCTURAL1/30/2019 2/6/2019 FAIL
DetailsJoe Bruce
See structural comment in the Agency Comments folder for remaining issue to address. Provide a complete written response outlining the analysis method you are taking responsibility for.
Plan resubmittals received  1/30/2019 DONE
DetailsJoe Bruce
Routing - FIRE1/29/20191/29/20191/29/2019 PASS
DetailsErika Akin
Attached comments to case
Routing - PLAN CHECK1/17/2019 1/28/2019 PASS
DetailsJoe Bruce
Routing Off Site - STRUCTURAL1/17/2019 1/28/2019 FAIL
DetailsJoe Bruce
Routing PW Sewer Design1/17/2019 1/23/2019 FAIL
DetailsDeAnn Brown
Routing - Design Review1/17/2019 1/18/2019 PASS
DetailsKatelyn Menuge
Plan resubmittals received  1/17/2019 DONE
DetailsJoe Bruce
Plan resubmittals received  1/15/2019 DONE
DetailsJoe Bruce
Routing - FIRE11/14/201811/14/201812/12/2018 FAIL
DetailsErika Akin
Plan resubmittals requested  12/12/2018 DONE
DetailsJoe Bruce
Routing - PLAN CHECK11/14/2018 12/7/2018 FAIL
DetailsJoe Bruce
Routing Off Site - STRUCTURAL11/14/2018 11/29/2018 FAIL
DetailsJoe Bruce
Routing - MECHANICAL11/14/2018 11/26/2018 PASS
DetailsTroy James
Routing PW Drainage11/14/2018 11/20/2018 PASS
DetailsBrian Murphy
Routing - PLUMBING11/14/2018 11/19/2018 PASS
DetailsDan Ediger
Routing - Design Review11/14/2018 11/16/2018 FAIL
DetailsKatelyn Menuge
Routing PW Street Lights11/14/2018 11/15/2018 PASS
DetailsTom Marshall
Routing PW Sewer Design11/14/2018 11/15/2018 FAIL
DetailsDeAnn Brown
Routing - PLANNING11/14/2018 11/15/2018 PASS
DetailsLeon Letson
Routing PW Solid Waste11/14/2018 11/14/2018 PASS
DetailsEvan Carpenter
Routing - Addressing11/14/2018 11/14/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS11/14/2018 11/14/2018 PASS
DetailsAngela Hardy
Routing - Erosion and Sediment11/14/2018 11/14/2018 CANC
DetailsAndy J. Long
Intake Approval  11/7/2018 PASS
DetailsJavier Guzman
Intake Approval  10/25/2018 FAIL
DetailsJavier Guzman
Application received 10/22/201810/22/2018 DONE
Second Notice 8/21/2020   
Routing PW Sewer Design1/30/2019