CHANGE STATUS TO (ISS) | | | 8/12/2020 | | DONE |
|
|
|
|
Routing - Design Review | 8/11/2020 | | 8/11/2020 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Wall Bracing | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | NR |
Tell Riley
|
|
|
Hold downs Phone #: ###-#### Inspection requested via web by Lee Scott//several hold downs are incorrect size//hold downs for interior shear wall need installed//
|
BLD-Energy code compliance | 7/7/2020 | 7/7/2020 | 7/7/2020 | P | PART |
Tell Riley
|
|
|
Check insulation at pre rock areas for tubs Phone #: ###-#### Inspection requested via web by Travis Blackburn//1st through 3rd floor ok for tub areas//4th floor not accesible at time of inspection//
|
BLD-Framing/Rough-in | 6/30/2020 | 7/1/2020 | 7/1/2020 | A | PART |
Tell Riley
|
|
|
Pre rock areas for tubs and plumbing walls Phone #: ###-#### Inspection requested via web by Travis Blackburn//add bolts 1st floor as discussed//add studs where needed//pending electrical in areas to be covered//
|
BLD-Framing/Rough-in | 6/24/2020 | 6/25/2020 | 6/25/2020 | A | PART |
Tell Riley
|
|
|
Start checking trusses at 4th floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//trusses were reviewed, one truss backward, one truss brace on wrong web, add nails to all hangers//provide clarificationf for hangers on 4 corners that spec to be installed upside down-and complete install//add H2.5s at corridor exterior bearing walls according to truss docs//
|
BLD-Wall Bracing | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | PART |
Tell Riley
|
|
|
Inspection for missed straps at south balconies for exterior cover. Phone #: ###-#### Inspection requested via web by Travis Blackburn//exterior straps nailed and exterior nailing ok//still need to check other hardware//
|
BLD-Framing/Rough-in | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | PART |
Tell Riley
|
|
|
Partial framing inspection for 2hr lid in west corridor Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to install shaft liner//
|
BLD-Wall Bracing | 4/8/2020 | 4/10/2020 | 4/10/2020 | A | PART |
Tell Riley
|
|
|
Inspection for floor to floor strapping and roof tie downs for cover of upper level roof eves with fire protection sheetrock Phone #: ###-#### Inspection requested via web by Travis Blackburn// north and west walls only, exterior strapping and nailing ok// eaves ok where h2.5s installed//
|
BLD-Wall Bracing | 4/2/2020 | 4/3/2020 | 4/3/2020 | P | PART |
Tell Riley
|
|
|
Shear panels only on exterior of bldg. Hardware next week Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to add hot dip galvanized nails at coridors, and areas marked//will check hardware in next inspection//
|
BLD-Aging Inspection | 3/31/2020 | 3/31/2020 | 3/31/2020 | | PASS |
Tell Riley
|
|
|
WIP
|
BLD-Concrete | 12/17/2019 | 12/18/2019 | 12/18/2019 | A | PEND |
Tell Riley
|
|
|
We are pouring the patios for building H and L tomorrow at 11. Would like inspection before that. Phone #: ###-#### Inspection requested via web by Matt Perry//poured early--specials onsite//pend specials//
|
BLD-Concrete | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PASS |
Tell Riley
|
|
|
Pouring the corridor for building H tomorrow morning at 6:30am Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials//
|
Extend Permit 90/180 days | 11/14/2019 | 11/15/2019 | 11/15/2019 | P | CANC |
Tell Riley
|
|
|
The slab for building H will be poured on Monday at 6:30am. Would like to get it inspected Friday late afternoon. Phone #: ###-#### Inspection requested via web by Matt Perry
|
BLD-Concrete | 11/14/2019 | 11/15/2019 | 11/15/2019 | P | PASS |
Tell Riley
|
|
|
The slab for building H will be poured on Monday at 6:30am. Would like to get it inspected Friday late afternoon. Phone #: ###-#### Inspection requested via web by Matt Perry//pending specials//
|
BLD-Concrete | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | PEND |
Dave Hannah
|
|
|
The slab for building H will be poured on Monday at 6:30am. Would like to get it inspected Friday late afternoon. Phone #: ###-#### Inspection requested via web by Matt Perry
|
BLD-Concrete | 10/30/2019 | 10/31/2019 | 11/1/2019 | P | PASS |
Dave Hannah
|
|
|
Pouring the stem walls at 7am Friday 11/1. Phone #: ###-#### Inspection requested via web by Matt Perry
|
BLD-Concrete | 10/29/2019 | 10/30/2019 | 10/30/2019 | P | NR |
Tell Riley
|
|
|
Stem wall inspection and footing for elevator shaft inspection. Pour will be Friday 11/1. Phone #: ###-#### Inspection requested via web by Matt Perry//not ready//will reschedule//
|
BLD-Footing | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PART |
Tell Riley
|
|
|
Pour time is at 1pm. Thanks Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//
|
BLD-Footing | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | CANC |
Tell Riley
|
|
|
Late inspection requested. Concrete pour is early Tuesday morning and crew will be forming and tying bar all day. Phone #: ###-#### >> Inspection requested via web by Travis Blackburn Inspection cancelled from web by: Travis Blackburn
|
Issue PAID IN FULL permit | | | 8/15/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/15/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/13/2019 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT OHTER 13 PERMITS AND VOIDED PERMIT HAS PLAN CHECK FEES
met
RP
GC
Revised Certificate of Value
|
Routing PW Street Lights | 8/12/2019 | | 8/12/2019 | | PASS |
Tom Marshall
|
|
|
|
Plan assigned to (CJW) | 3/11/2019 | 3/11/2019 | 8/10/2019 | | PASS |
Carl Westfall
|
|
|
* (2nd done) 04/08/19 (new buildings - 25 days) (eplan) Village East Apartments (H) (approved pending structural)
|
Plan Reviewer's activity | | | 8/10/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for all buildings.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2019 | | DONE |
|
|
|
|
Routing - Design Review | 8/5/2019 | | 8/5/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - FIRE | 7/9/2019 | 7/9/2019 | 7/16/2019 | | PASS |
Mark Scharfen
|
|
|
07/16-Village East Building H resubmittal. MS. Completed fire review. Uploaded rev_fire 07.16.2019.pdf. All permits ok on fire.
|
Routing PW Drainage | 7/15/2019 | | 7/15/2019 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 7/8/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for the 3rd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Routing - FIRE | 6/13/2019 | 6/13/2019 | 6/24/2019 | | FAIL |
Mark Scharfen
|
|
|
06/26-Village East building H-Completed review 06.24.2019-uploaded rev_fire 06.24.2019.pdf and emailed architect.
|
Routing - Design Review | 6/17/2019 | | 6/17/2019 | | FAIL |
Andrea Tuning
|
|
|
A total of 272 bicycle parking spaces will be required. A minimum of 68 of the bicycle parking spaces are required to be covered. To provide a safe, covered and efficient location for the bicycles, design the spaces to be a minimum of 6-feet long and 2.5 feet wide and have an overhead clearance of 7-feet if covered. A 4-foot wide aisle is required between rows of bicycle parking or nearby walls. Stationary racks shall be located on improved non-permeable surfaces and anchored to the ground. A detail of the rack and how it is attached to the wall should be submitted with the building permit.
Vertical curbing shall be utilized adjacent to all landscaping and pedestrian walk ways. Permanent wheel restraints may be utilized in lieu of curbing adjacent to pedestrian walk ways.
All interior and terminal planter islands shall provide at least one Class II tree within all of the interior and terminal planters.
Provide an easement for portions of the Valley Regional transit stop located on private property.
Continue to work with staff to provide a cohesive and quality exterior building design in regard to material breaks, the application of brick on each building and the color palette for the development. This may include providing a brick wainscot or brick corner elements on each building, reevaluating the location of material breaks and further refining the color palette.
Employ techniques to recess windows above the ground floor a minimum of 2-inches from the façade or incorporated window trim at least 4-inches in width. Submit a window detail showing this recess.
|
Plan Reviewer's activity | | | 6/13/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for the 2nd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Route to Impact Fee Review | 4/26/2019 | 4/29/2019 | 4/26/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/11/2019 | | 4/26/2019 | | FAIL |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 4/26/2019 | | DONE |
|
|
|
|
1st review completed | | | 4/26/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/11/2019 | | 4/25/2019 | | PASS |
Andy J. Long
|
|
|
see ESC19-00181 for details
|
Routing - FIRE | 3/11/2019 | 3/11/2019 | 4/12/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 04.12.2019.pdf
|
Routing Off Site - STRUCTURAL | 3/11/2019 | | 3/27/2019 | | FAIL |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing PW Sewer Design | 3/12/2019 | | 3/26/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 3/12/2019 | | 3/21/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 3/12/2019 | | 3/21/2019 | | FAIL |
Brian Murphy
|
|
|
|
Routing - PLANNING | 3/11/2019 | | 3/19/2019 | | FAIL |
Leon Letson
|
|
|
See DR comments
|
Routing - MECHANICAL | 3/11/2019 | | 3/15/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/11/2019 | | 3/13/2019 | | FAIL |
Andrea Tuning
|
|
|
|
Routing - Addressing | 3/11/2019 | | 3/12/2019 | | PASS |
Doug Chausow
|
|
|
Bldg H: 11950 W Fairview Ave
|
Routing - PUBLIC WORKS | 3/11/2019 | | 3/12/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Street Lights | 3/12/2019 | | 3/12/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 3/11/2019 | | 3/11/2019 | | PASS |
Daryl Spivey
|
|
|
Meet suds relief requirements and per ISPC.
|
Intake Approval | | | 3/5/2019 | | PASS |
|
|
|
|
Application received | | | 2/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 21 2019 5:02PM
|