CHANGE STATUS TO (ISS) | | | 8/12/2020 | | DONE |
|
|
|
Status altered after DR routing added and completed - permit needs to stay in issued status.
|
Routing - Design Review | 8/11/2020 | | 8/11/2020 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Framing/Rough-in | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | PART |
Tell Riley
|
|
|
Roof Phone #: ###-#### Inspection requested via web by Lee Scott//ok on most trusses//some trusses inwrong locatin and bearing points//lee will have truss fix for these trusses from manufacturer//
|
BLD-Wall Bracing | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Tell Riley
|
|
|
Hold downs Phone #: ###-#### Inspection requested via web by Lee Scott//one hold down on interior needs to be changed out for correct size//others appear to meet shcedule//
|
BLD-Framing/Rough-in | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Tell Riley
|
|
|
Roof framing Phone #: ###-#### Inspection requested via web by Lee Scott//north east block of building trusses//will need to check other 2 blocks// one girder installed in wrong direction//other truss bracing appears to be ok//
|
BLD-Wall Bracing | 6/10/2020 | 6/11/2020 | 6/11/2020 | P | PART |
Tell Riley
|
|
|
Inspect floor to floor straps for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//exterior floor to floor strapping ok--north end 4 straps need to be changed to meet requirements//
|
BLD-Framing/Rough-in | 5/20/2020 | 5/20/2020 | 5/20/2020 | P | PART |
Tell Riley
|
|
|
Inspect truss anchors (H2.5''s) at balcony beams for rated soffits to be hung and trusses at top of stairways for shaftliner assembly to go in. Phone #: ###-#### Inspection requested via web by Travis Blackburn//add hangers, nails in hangers as noted//truss fix was reviewed onsite for modified truss over elevator landing area//
|
BLD-Wall Bracing | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PART |
Tell Riley
|
|
|
Shear panels only. Need to load the building a little before floor to floor straps Phone #: ###-#### Inspection requested via web by Travis Blackburn//nailing only on exterior and corridor//add nails as discussed on walk through//several areas in corridors//
|
BLD-Concrete | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | DEFR |
Tell Riley
|
|
|
Sorry forgot to add this inspection. We are pouring the corridor for building J today at 11. Thanks Phone #: ###-#### Inspection requested via web by Matt Perry//specials will be onsite//defer to special inspections//
|
BLD-Concrete | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PASS |
Tell Riley
|
|
|
Please inspect after 11am, we will be finished with set up and might have to cover the slab. Thanks Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials and elevated bar for clearances//
|
BLD-Concrete | 11/18/2019 | 11/19/2019 | 11/19/2019 | P | PASS |
Tell Riley
|
|
|
The walls for building J are getting poured Wednesday about noon Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials and rebar clearances//
|
BLD-Footing | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | PART |
Tell Riley
|
|
|
Pouring the footing for Building J tomorrow ( Wednesday) at 2pm. Phone #: ###-#### Inspection requested via web by Matt Perry//ok per plans pending specials//looked at footings for elevator as well--ok per details on structurals//
|
Issue PAID IN FULL permit | | | 8/15/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/15/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/13/2019 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT OHTER 13 PERMITS AND VOIDED PERMIT HAS PLAN CHECK FEES
met
RP
GC
Revised Certificate of Value
|
Routing PW Street Lights | 8/12/2019 | | 8/12/2019 | | PASS |
Tom Marshall
|
|
|
|
Plan assigned to (CJW) | 3/11/2019 | 3/11/2019 | 8/10/2019 | | PASS |
Carl Westfall
|
|
|
* (2nd done) 04/08/19 (new buildings - 25 days) (eplan) Village East Apartments (J) (approved pending structural)
|
Plan Reviewer's activity | | | 8/10/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for all buildings.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2019 | | DONE |
|
|
|
|
Routing - Design Review | 8/5/2019 | | 8/5/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - FIRE | 7/9/2019 | 7/9/2019 | 7/16/2019 | | PASS |
Mark Scharfen
|
|
|
07/16-Village East building J resubmittal. MS. completed fire review. Uploaded rev_fire 07.16.2019.pdf. All permits ok on fire.
|
Routing PW Drainage | 7/15/2019 | | 7/15/2019 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 7/8/2019 | | DEFR |
|
|
|
See the routing under permit BLD19-00526 for the 3rd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Routing - FIRE | 6/13/2019 | 6/13/2019 | 6/24/2019 | | FAIL |
Mark Scharfen
|
|
|
06/26-Village East building J resubmittal MS. completed fire review, uploaded rev_fire 06.24.2019.pdf and emailed to architect.
|
Routing - Design Review | 6/17/2019 | | 6/17/2019 | | FAIL |
Andrea Tuning
|
|
|
A total of 272 bicycle parking spaces will be required. A minimum of 68 of the bicycle parking spaces are required to be covered. To provide a safe, covered and efficient location for the bicycles, design the spaces to be a minimum of 6-feet long and 2.5 feet wide and have an overhead clearance of 7-feet if covered. A 4-foot wide aisle is required between rows of bicycle parking or nearby walls. Stationary racks shall be located on improved non-permeable surfaces and anchored to the ground. A detail of the rack and how it is attached to the wall should be submitted with the building permit.
Vertical curbing shall be utilized adjacent to all landscaping and pedestrian walk ways. Permanent wheel restraints may be utilized in lieu of curbing adjacent to pedestrian walk ways.
All interior and terminal planter islands shall provide at least one Class II tree within all of the interior and terminal planters.
Provide an easement for portions of the Valley Regional transit stop located on private property.
Continue to work with staff to provide a cohesive and quality exterior building design in regard to material breaks, the application of brick on each building and the color palette for the development. This may include providing a brick wainscot or brick corner elements on each building, reevaluating the location of material breaks and further refining the color palette.
Employ techniques to recess windows above the ground floor a minimum of 2-inches from the façade or incorporated window trim at least 4-inches in width. Submit a window detail showing this recess.
|
Plan Reviewer's activity | | | 6/13/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for the 2nd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Route to Impact Fee Review | 4/26/2019 | 4/29/2019 | 4/26/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/11/2019 | | 4/26/2019 | | FAIL |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 4/26/2019 | | DONE |
|
|
|
|
1st review completed | | | 4/26/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/11/2019 | | 4/25/2019 | | PASS |
Andy J. Long
|
|
|
see ESC19-00181 for details
|
Routing - FIRE | 3/11/2019 | 3/11/2019 | 4/12/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 04.12.2019.pdf
|
Routing Off Site - STRUCTURAL | 3/11/2019 | | 3/27/2019 | | FAIL |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing PW Sewer Design | 3/12/2019 | | 3/26/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 3/12/2019 | | 3/21/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 3/12/2019 | | 3/21/2019 | | FAIL |
Brian Murphy
|
|
|
|
Routing - PLANNING | 3/11/2019 | | 3/19/2019 | | FAIL |
Leon Letson
|
|
|
See DR comments
|
Routing - MECHANICAL | 3/11/2019 | | 3/15/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/11/2019 | | 3/13/2019 | | FAIL |
Andrea Tuning
|
|
|
|
Routing - Addressing | 3/11/2019 | | 3/12/2019 | | PASS |
Doug Chausow
|
|
|
Bldg J: 11922 W Fairview Ave
|
Routing - PUBLIC WORKS | 3/11/2019 | | 3/12/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Street Lights | 3/12/2019 | | 3/12/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 3/11/2019 | | 3/11/2019 | | PASS |
Daryl Spivey
|
|
|
Meet suds relief requirements and per ISPC.
|
Intake Approval | | | 3/5/2019 | | PASS |
|
|
|
|
Application received | | | 2/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 21 2019 5:02PM
|