BLD-Aging Inspection | 8/7/2020 | 8/7/2020 | 8/7/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Aging Inspection | 3/26/2020 | 3/26/2020 | 3/26/2020 | | PASS |
Tell Riley
|
|
|
WIP
|
BLD-Conference | 12/13/2019 | 12/13/2019 | 12/13/2019 | A | DONE |
Tell Riley
|
|
|
discussed with owners engineer, Shawn Reeder, the pole building, he is designing some changes for compliance as no inspections have been completed//advised once design is complete to submit for plan modification//
|
BLD-Conference | 12/11/2019 | 12/11/2019 | 12/11/2019 | A | DONE |
Tell Riley
|
|
|
Gary--###-####//gary has engineered fix for beams in garage//need to have engineer verify and ok footings used for the pole barn// setbacks appear to be ok per plan//
|
BLD-Conference | 11/12/2019 | 11/19/2019 | 11/19/2019 | A | DONE |
Tell Riley
|
|
|
follow up on CN for pole structure....//stopped by, no progress on pole structure..//
|
BLD-Framing/Rough-in | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | PART |
Tell Riley
|
|
|
call for access- Gary Phone #: ###-####//framing approved for existing conversion only//was discrepancies with previous inspection--walked through and ok to cover//will need to get certification/verification of pole structure by engineer as no inspections have been completed//
|
BLD-Wall Bracing | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | CANC |
Tell Riley
|
|
|
call for access- Gary Phone #: ###-####
|
BLD-Foundation | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | NR |
Tell Riley
|
|
|
Call for access- Gary Phone #: ###-####//gary will be getting back with me on the footings//engineer will need to verify structure as no inspections have been completed//
|
BLD-Conference | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | DONE |
Tell Riley
|
|
|
Correction notice issued//no isnpections have been requested for the addtion of the pole structure//structure is almost complete//will need verification of required footings///
|
BLD-Aging Inspection | 10/10/2019 | 10/10/2019 | 10/10/2019 | | PASS |
Tell Riley
|
|
|
Expires: 11/25/19
|
BLD-Framing/Rough-in | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | PART |
Jim Sly
|
|
|
Bill- please call for access Phone #: ###-#### Framing OK for inside existing Garage......Only.
|
BLD-Conference | 5/14/2019 | 5/17/2019 | 5/17/2019 | A | NH |
Jim Sly
|
|
|
Bill Phone #: ###-#### Called......no answer.......Went to address......no humans on site.
|
Routing Walk-In (BLD) | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Josh Bogle
|
|
|
go over differnet option for construction - had a wonderful discussion
|
OVERRIDE | | | 4/4/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 3/29/2019 | 3/29/2019 | 4/4/2019 | | PASS |
Josh Bogle
|
|
|
4/4 addition, paper
|
Issue PAID IN FULL permit | | | 4/4/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/2/2019 | | 4/4/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 4/4/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 4/4/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 4/4/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/29/2019 | | 4/2/2019 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (BLD) | 3/29/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Josh Bogle
|
|
|
took in as a level two - routed to Mechanical
|
Routing Walk-In (Zoning) | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | DONE |
David Moser
|
|
|
|
Routing Walk-In (BLD) | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 2/22/2019 | | 2/22/2019 | | FAIL |
Josh Bogle
|
|
|
needs engineering, other details, & full sized plan
|
1st review completed | | | 2/22/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 2/22/2019 | | | |
|
|
|
|