BLD-Final | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | PASS |
Dave Hannah
|
|
|
*Screened* Damon, call for access code Phone #: ###-####
|
DOC - Permit Finaled | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 7/22/2020 | 7/23/2020 | 7/23/2020 | P | FAIL |
Tell Riley
|
|
|
Damon - */Screened*/ Phone #: ###-####//need to have hard surface turnaround per plans or provide approval from zoning//currently only a 20 foot drive connected to common driveway//
|
BLD-Blower Door Test Results | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | DONE |
Tell Riley
|
|
|
5.9 ACH 50
|
Routing - PLANNING | 7/23/2020 | | 7/23/2020 | | PASS |
Nicolette Womack
|
|
|
Confirmed driveway as built satisfies requirements for shared driveway. Turn around not required as fire access is within permitted distance from Spaulding.
|
BLD-Blower Door Test Results | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | CANC |
Tell Riley
|
|
|
|
BLD-Final | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | FAIL |
Tell Riley
|
|
|
Daiman *cleared* Phone #: ###-####//still needs driveway or zoning approval//
|
BLD-Final | 4/7/2020 | 4/8/2020 | 4/8/2020 | P | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Damion Jordan//CN issued//need to finish backfill around foundation on west and south side//need blower door test//need to post insulation certificate//need to complete shared driveway and turnaround or provide zoning approval//add house numbers to home//
|
Plan Reviewer's activity | | | 4/8/2020 | | |
Rob Patrick
|
|
|
Applicant phoned and we discussed access requirements to the loft area above the master bedroom and bath. Applicant stated that area was strictly for storage and was not going to be living space. This space can only be used for "Storage" space and can not be used for living space.
|
BLD-Energy code compliance | 1/23/2020 | 1/23/2020 | 1/23/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 1/22/2020 | 1/23/2020 | 1/23/2020 | P | PART |
Brandon Shaw
|
|
|
East entry and North walls, OK to cover exterior only...
|
BLD-Framing/Rough-in | 1/17/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Tell Riley
|
|
|
damon Phone #: ###-####//corrections made from walk through//ok to insulate only//will need fireplace sign off prior to cover//
|
BLD-Framing/Rough-in | 1/16/2020 | 1/17/2020 | 1/17/2020 | P | NR |
Tell Riley
|
|
|
Damon Phone #: ###-####//need mechanical pass and fire place rough in passed//did a walk through and marked areas for anchor bolts and framing corrections//
|
BLD-Wall Bracing | 12/13/2019 | 12/16/2019 | 12/16/2019 | A | PART |
Tell Riley
|
|
|
Damon Phone #: ###-####//correction notice issued for hold down location that does not reflect location noted by engineer//other changes on garage ok per plans\\
|
CHANGE STATUS TO (ISS) | | | 12/13/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 12/10/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 12/5/2019 | 12/5/2019 | 12/10/2019 | | DONE |
Rob Patrick
|
|
|
Plan Mod...received engineering changes, still waiting for dwg updates. 12/09/19 Failed for Planning comment
|
Routing - PLAN CHECK | 12/10/2019 | | 12/10/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 12/10/2019 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
BLD-Wall Bracing | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PART |
Tell Riley
|
|
|
shear // Damion Phone #: ###-####//nailing and hold downs ok per engineering provided//need engineers ok on window location and added door in garage//do not cover these areas//
|
Routing - PLANNING | 12/9/2019 | | 12/9/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - PLAN CHECK | 12/9/2019 | | 12/9/2019 | | FAIL |
Rob Patrick
|
|
|
Failed for Planning comment.
|
Routing - PLAN CHECK | 12/9/2019 | | 12/9/2019 | | FAIL |
Rob Patrick
|
|
|
Planning note concerning driveway.
|
BLD-Framing/Rough-in | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | NR |
Tell Riley
|
|
|
Bob Phone #: ###-####//need to submit new engineering for shear walls//call for re-inspection//
|
Plan Modification Accepted | | | 12/5/2019 | | DONE |
|
|
|
truss in garage engineering info, location of windows to match elevation engineered provided for framing, adding on closet in bedroom to take over part of garage, and putting in 16ft window in the great room
|
BLD-Conference | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | DONE |
Tell Riley
|
|
|
Damon Phone #: ###-####//questions on loft and a plan change///advised to submit a plan mod for approval//
|
Routing - MECHANICAL | 11/8/2019 | | 11/8/2019 | | PASS |
Chad Schwendiman
|
|
|
Revised acca report
|
BLD-Foundation | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Bob Archibald
|
|
|
Spoke with Clint From Boise Division Project II @ ###-####. Clint informed me that the approximate 4" enchroachment was acceptable.
|
BLD-Foundation | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PART |
Tell Riley
|
|
|
call half hour before to meet // damion Phone #: ###-####//discussed easment//no pins fpr easement--will need pins for easment or written confirmation of placement from canal company//notified Damion he can proceed at his own risk--we will still need confirmation from canal company for setbacks//he will notify me when written documentation is recieved//--per Bob
|
BLD-Footing | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | FAIL |
Tell Riley
|
|
|
damion Phone #: ###-####//no pins onsite observed for easment of canal// locate pins for easment verification and setback requirements//
|
BLD-Conference | 8/9/2019 | 8/12/2019 | 8/12/2019 | P | DONE |
Tell Riley
|
|
|
check on project..footings and wall may have been poured--footing inspection failed on 7/12/2019//footings and foundation have been poured//footing inspection failed on 7/12 (no pins to verify setbacks for canal easment)//correctin notice issued to locate pins and verify easement setbacks prior to continuing on preject//
|
BLD-Footing | 7/12/2019 | 7/12/2019 | 7/12/2019 | P | FAIL |
Tell Riley
|
|
|
need to string easment line for canal//NE corner of house will be on easment line//call for re-inspection//
|
BLD-Conference | 7/12/2019 | 7/12/2019 | 7/12/2019 | P | CANC |
Tell Riley
|
|
|
damion Phone #: ###-####
|
Meeting | | | 6/20/2019 | | DONE |
|
|
|
emailed damion that there are still fees due before issuance
|
Issue PAID IN FULL permit | | | 6/20/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/20/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/18/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 4/3/2019 | 4/3/2019 | 6/18/2019 | | DONE |
Rob Patrick
|
|
|
04/16 sfd L1 ePlan...04/11 Failed...04/23 Failed...06/06 Failed
|
Routing - PLAN CHECK | 6/18/2019 | | 6/18/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/18/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/12/2019 | | 6/12/2019 | | FAIL |
Rob Patrick
|
|
|
Remove patio cover on sheets 3&5; Add Braced Wall Lines to sheet 4
|
Routing - PLAN CHECK | 6/6/2019 | | 6/6/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing - PLAN CHECK | 4/23/2019 | | 4/23/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections required
|
1st review completed | | | 4/11/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLAN CHECK | 4/3/2019 | | 4/11/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Route to Impact Fee Review | 4/3/2019 | 4/6/2019 | 4/4/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/3/2019 | | 4/4/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/3/2019 | | 4/3/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 4/3/2019 | | 4/3/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/3/2019 | | 4/3/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 4/3/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/3/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/13/2019 | | FAIL |
|
|
|
Please provide updated value for entire project covered under this permit 1602 sq. ft. and identify fixture (two circles next to wetbar sink) in "Man Cave".
|
Intake Approval | | | 3/7/2019 | | FAIL |
|
|
|
Please provide 1. Manual J
2. Indicate the location of the furnace and air conditioner on your plans
|
Application received | | | 2/23/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 23 2019 3:22PM
|