Third Notice | | 4/8/2020 | 4/9/2020 | | DONE |
|
|
|
This permit finaled on the web by Sheila Winkler
|
Second Notice | | 3/15/2020 | 4/3/2020 | | DONE |
|
|
|
mailed 4-6-2020
|
First Notice | | 2/22/2020 | 3/5/2020 | | DONE |
|
|
|
mailed 3-6-20
|
BLD-Final | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter
|
FIRE-Final Inspection | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Zach Carter
|
Permanent Occupancy | | | 2/12/2020 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | FAIL |
Jim Page
|
|
|
Exit signage needs to match what was submitted on city approved drawings, provide code compliant hardware on NW exit door, riser room is not 1 hour fire rated due to multiple holes in wall, provide and install knox box. Mount fire extinguishers at max 48" to mechanism as discussed. Still need to verify emergency operation of all emergency lights. FIR permit for fire sprinklers must be finaled before life safety can be completed. GR
Phone #: ###-#### Inspection requested via web by Zach Carter
|
BLD-Final | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Zach Carter Inspection cancelled from web by: Zach Carter
|
BLD-Final | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//need fire life safety, sprinkler and fire alarm finals// will need to reshedule//
|
Zoning Approval | 2/7/2020 | 2/7/2020 | 2/7/2020 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 12/23/2020 | 12/24/2020 | 2/5/2020 | P | PART |
Tell Riley
|
|
|
Per Tell, framing inspection put on Foundation permit. Switching it to BLD19-00843 2-5-2020 // new GB over existing framing//insulation ok, vapor barrier installed//no electrical or plumbing//
|
CHANGE STATUS TO (ISS) | | | 1/29/2020 | | DONE |
|
|
|
per carl m didn't mean to put back in REV
|
BLD-Conference | 12/12/2019 | 12/16/2019 | 12/16/2019 | A | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//site walk through//accesible ramp to steep on outside of building--discussed options to make compliant//accessible ramp inside filled with insulation-talk with Troy about depth of fill//will need framing for tall building area prior to cover//
|
BLD-Conference | 11/12/2019 | 11/15/2019 | 11/15/2019 | A | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//discussed RFI for ramp --approved as is by engineer for structural//discussed climbing wall structures and verifiying permits and special inspections//
|
FIRE-Conference | 11/12/2019 | 11/14/2019 | 11/14/2019 | P | DONE |
Troy Cobbley
|
|
|
We discussed possible combustible concealed spaces caused by the climbing wall construction. Phone #: ###-#### Inspection requested via web by Zach Carter
|
BLD-Framing/Rough-in | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PART |
Tell Riley
|
|
|
Zach Phone #: ###-####//need to provide mod for construction changes to ramp//vestibule, bathrooms ok when fire sprinklers have passed--discussed with Troy and advised Zach to schedule fire conference for areas behind rock walls//
|
CHANGE STATUS TO (ISS) | | | 10/2/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/27/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 8/13/2019 | 8/13/2019 | 9/27/2019 | | DONE |
Julie Romig
|
|
|
09/30 - 2nd Rev - Plan Mod - The Commons Climbing Gym
|
Permit Ready to Issue | | | 9/27/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/24/2019 | | 9/24/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/24/2019 | | 9/24/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - PLUMBING | 9/19/2019 | | 9/19/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC. With DCVA as premise protection.
|
Routing Off Site - STRUCTURAL | 9/13/2019 | | 9/18/2019 | | PASS |
Julie Romig
|
|
|
Stapley
|
Routing - PLAN CHECK | 9/13/2019 | | 9/18/2019 | | PASS |
Julie Romig
|
|
|
|
Plan Modification Accepted | | | 8/13/2019 | | DONE |
|
|
|
plan mod accepted
|
BLD-Conference | 7/22/2019 | 7/24/2019 | 7/24/2019 | A | DONE |
Tell Riley
|
|
|
Zack Phone #: ###-####//discuss project and advised Zack to submit plan changes to plan review for approval//
|
BLD-Foundation | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Pending special inspection...
|
BLD-Footing | 7/3/2019 | 7/3/2019 | 7/3/2019 | P | PART |
Tell Riley
|
|
|
Zach Phone #: ###-####//concrete already poured//specials were completed to epoxy, rebar and concrete//
|
Issue PAID IN FULL permit | | | 6/25/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/25/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/21/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 6/21/2019 | | DONE |
|
|
|
Met
NEED
emailed forms to zcarter@wbtbc.com*PLEASE SEND OWNER A NOTICE WHEN FEES ARE APPLIED*
GC
Revised Certificate of Value
|
Routing - PUBLIC WORKS | 5/31/2019 | | 6/21/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2019 | | 6/21/2019 | | PASS |
Angela Hardy
|
|
|
|
Plan assigned to (JAR) | 4/4/2019 | 4/4/2019 | 6/20/2019 | | DONE |
Julie Romig
|
|
|
06/20 - 3rd Rev - 1st Rev Comp - 502 The Commons Climbing Gym
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/17/2019 | | 6/19/2019 | | PASS |
Julie Romig
|
|
|
3rd Building Review
|
Routing Off Site - STRUCTURAL | 6/17/2019 | | 6/18/2019 | | PASS |
Julie Romig
|
|
|
5th Review
|
Routing - Design Review | 6/17/2019 | | 6/17/2019 | | PASS |
Andrea Tuning
|
|
|
Plans were redlined to require the landscape planter and the pedestrian walkway to remain.
|
Routing - PLAN CHECK | 5/31/2019 | | 6/8/2019 | | FAIL |
Julie Romig
|
|
|
IBC plan review report emailed to architect, contractor, owner
|
Routing Off Site - STRUCTURAL | 6/5/2019 | | 6/8/2019 | | FAIL |
Julie Romig
|
|
|
4th Review
|
Routing - FIRE | 5/31/2019 | 6/3/2019 | 6/7/2019 | | PASS |
Mark Scharfen
|
|
|
06.07.2019-Completed IFC review. Uploaded rev_fire 06.07.2019.pdf. Passed review.
|
Routing - Design Review | 5/31/2019 | | 6/4/2019 | | FAIL |
Andrea Tuning
|
|
|
The proposed bicycle parking rack is not an approved bicycle rack and the parking pad will not accomodate the 5 required bicycle parking spaces.
|
Routing - PLUMBING | 6/3/2019 | | 6/3/2019 | | PASS |
Dan Ediger
|
|
|
3rd Review
Per plans and specifications
|
Routing Off Site - STRUCTURAL | 5/31/2019 | | 6/3/2019 | | FAIL |
Julie Romig
|
|
|
3rd Review - Provide updated foundation plan and details to address the access ramp.
|
Routing - MECHANICAL | 5/31/2019 | | 6/3/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 5/31/2019 | | 6/3/2019 | | FAIL |
Dan Ediger
|
|
|
Provide a 3" floor sink in the mechanical room.
Show all hot water piping, sizing and insulation requirements.
|
Routing Off Site - STRUCTURAL | 5/24/2019 | | 5/29/2019 | | FAIL |
Julie Romig
|
|
|
2nd Review - Structural resubmittal routed to Stapley via email for 2nd Review
|
Plan Reviewer's activity | | | 5/28/2019 | | DONE |
|
|
|
Received revised Site Plan from architect's office addressing fire access comments. Emailed plan to Josh Wilson (Design Review) and Mark Schafren (Fire) for input.
|
Route to Impact Fee Review | 5/15/2019 | 5/18/2019 | 5/15/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 4/4/2019 | 4/4/2019 | 5/14/2019 | | FAIL |
Mark Scharfen
|
|
|
05.14.2019-Completed IFC review. Uploaded Rev_fire 05.14.2019.pdf and emailed architect.
|
Routing - PLAN CHECK | 4/4/2019 | | 5/14/2019 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 5/14/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 4/4/2019 | | 4/18/2019 | | FAIL |
Julie Romig
|
|
|
1st Review - Stapley
|
Routing - MECHANICAL | 4/4/2019 | | 4/9/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/4/2019 | | 4/8/2019 | | PASS |
David Moser
|
|
|
SEE DRH19-00043
|
Routing - Addressing | 4/4/2019 | | 4/5/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/4/2019 | | 4/5/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 4/4/2019 | | 4/5/2019 | | FAIL |
Andrea Tuning
|
|
|
Provide a minimum of 5 bicycle parking spaces on the site. The parking spaces shall be a minimum of 6-feet long and 2.5-feet side and have an overhead clearance of 7-feet if covered. A 4-foot side aisle is required between rows of bicycle parking spaces or nearby walls. All bike racks are required to be located on an improved non-permeable surface and anchored to the ground. Submit cut sheets of the proposed bicycle parking racks and covers for final review and approval.
The new tree within the new planter island shall be an approved Class II tree within the Boise City Tree Selection Guide.
|
Routing - Erosion and Sediment | 4/4/2019 | | 4/4/2019 | | PASS |
Michael Zawacki
|
|
|
|
Routing - PLUMBING | 4/4/2019 | | 4/4/2019 | | FAIL |
Dan Ediger
|
|
|
Install a floor drain in the mechanical room per notes
|
Intake Approval | | | 4/4/2019 | | PASS |
Joe Bruce
|
|
|
Prescreen approved 04/04/19 by JHB
|
Intake Approval | | | 3/20/2019 | | FAIL |
Joe Bruce
|
|
|
Please provide the following to complete your prescreen:
1. Form #310 Statement of Special Inspections: Provide the additional pages with form #310 that denote the required type of inspections required. You can download the entire form for our website.
2. Please contact Michael Zawacki - mzawacki@cityofboise.org – ###-#### for the requirements for the Erosion and Sediment Control application. Since there is a new concrete slab being poured: an ESC permit will be required. Contact Michael for what will be required.
3. Fire extinguishers could not be located on the cover sheet. The F.E. could be located on the notes, but not located on the plan. Please provide locations.
4. Sheet S-101 could not be located in the drawings folder. Please upload this drawing.
5. Sheet E3.1 Lighting Compliance forms use the incorrect version of the IECC code. Please update to the 2105 IECC. Resubmit drawings with updated COMcheck.
|
Application received | | | 3/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 18 2019 10:27AM
|
Routing - Erosion and Sediment | 1/29/2020 | | | | |
|
|
|
|