BLD-Blower Door Test Results | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | DONE |
Tell Riley
|
|
|
4.45 ACH 50
|
BLD-Final | 11/13/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Tell Riley
|
|
|
Alex Phone #: ###-####///corrections made//
|
DOC - Permit Finaled | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | FAIL |
Tell Riley
|
|
|
Alex Phone #: ###-####//need blower door test//add step at door in garage//need fall prevention devices at windows with sill under 24" on 2nd floor//
|
Inspection Record Card- Bld | | | 11/5/2019 | | DONE |
|
|
|
|
BLD-Energy code compliance | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PASS |
Tell Riley
|
|
|
Alex Phone #: ###-####
|
BLD-Wall cover | 9/3/2019 | 9/4/2019 | 9/4/2019 | P | CANC |
Tell Riley
|
|
|
Alex Phone #: ###-####//only needs energy inspection//
|
BLD-Framing/Rough-in | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Mike Jordan
|
|
|
aLEX Phone #: ###-####
|
BLD-Framing/Rough-in | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | CANC |
Tell Riley
|
|
|
alex Phone #: ###-####
|
BLD-Wall Bracing | 7/24/2019 | 7/24/2019 | 7/24/2019 | P | PASS |
Tell Riley
|
|
|
ok//need to add holdowns a PFH//7/23/19 inspection completed//needed to change to wall bracing//canceled framing//
|
BLD-Framing/Rough-in | 7/22/2019 | 7/23/2019 | 7/24/2019 | A | CANC |
Tell Riley
|
|
|
Alex Phone #: ###-####//all panels blocked//nailing ok//add hold down at PFH per plans--will check at framing//
|
BLD-Conference | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | DONE |
Tell Riley
|
|
|
caller thinks the side setbacks are not 5'' Phone #: ###-####//verified setbacks at footing and foundation with concrete contractor from survey points on the lot//all points measured at the inspections were completed with a string line running from survey pins//
|
BLD-Foundation | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | CANC |
Tell Riley
|
|
|
Andras Phone #: ###-####//requested underfloor//no inspection required//
|
BLD-Foundation | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//rebar installed//vents ok//hold downs to be installed at framing//re-check setbacks--ok//
|
BLD-Footing | 6/21/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//setbacks ok per approved plans//rebar installed per plans//footing depth and width ok per plans//
|
Telephone call | | | 5/28/2019 | | DONE |
|
|
|
Emailed GC a reminder to please sign the permit and email it back
|
Place hold on job | 5/28/2019 | | 5/28/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
waiting for signed permit
|
Meeting | | | 5/24/2019 | | DONE |
|
|
|
GC paid for just the building permit fees over the counter. Informed him that there are fees remaining and once they are paid we can issue the permits.
GC is going to pay remaining fees online.
|
Inspection Record Card- Bld | | | 5/24/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/24/2019 | | DONE |
|
|
|
emailed permits to alex@adam-alexander.com
|
OVERRIDE | | | 5/9/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 4/1/2019 | 4/1/2019 | 5/9/2019 | | DONE |
Rob Patrick
|
|
|
04/12 sfd L1 ePlan...04/02 Failed...04/16 Failed
|
Routing - PLAN CHECK | 5/9/2019 | | 5/9/2019 | | PASS |
Rob Patrick
|
|
|
Please charge 3 hours of review time to this permit request.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/9/2019 | | DONE |
|
|
|
|
Routing - FIRE | 5/8/2019 | 5/8/2019 | 5/8/2019 | | PASS |
Lee G Meredith
|
|
|
Site plan indicates that fire sprinklers will be provided.
|
Routing - PLAN CHECK | 5/8/2019 | | 5/8/2019 | | FAIL |
Rob Patrick
|
|
|
B.W. calcs req'd
|
Routing - FIRE | 4/16/2019 | 4/16/2019 | 4/16/2019 | | FAIL |
Lee G Meredith
|
|
|
04/22 3863 Jackie Ln. LM Resubmittal.
Fire sprinkler system required due to access and hydrant distance. These items not addressed in this submittal. Permit will not be issued until this item has been resolved.
|
Routing - FIRE | 4/10/2019 | 4/10/2019 | 4/16/2019 | | FAIL |
|
|
|
04/16 3863 Jackie Ln. LM Resubmittal.
|
Routing - PLAN CHECK | 4/16/2019 | | 4/16/2019 | | FAIL |
Rob Patrick
|
|
|
Wall Brace corrections req'd
|
Routing - FIRE | 4/15/2019 | 4/15/2019 | 4/15/2019 | | FAIL |
Lee G Meredith
|
|
|
Fire sprinkler system required due to access and hydrant distance. These items not addressed in this submittal.
|
Routing - PLAN CHECK | 4/15/2019 | | 4/15/2019 | | FAIL |
Rob Patrick
|
|
|
04/15 Failed. Wall Bracing corrections req'd.
|
Routing - PLANNING | 4/15/2019 | | 4/15/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLANNING | 4/11/2019 | | 4/11/2019 | | FAIL |
Sue Cummings
|
|
|
Rename files.
|
Routing - PLAN CHECK | 4/10/2019 | | 4/11/2019 | | FAIL |
Rob Patrick
|
|
|
Renaming of files req'd.
|
Route to Impact Fee Review | 4/1/2019 | 4/4/2019 | 4/2/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 4/1/2019 | 4/1/2019 | 4/2/2019 | | FAIL |
Lee G Meredith
|
|
|
04/12 3836 Jackie Ln Residential.
House requires sprinklers due to excess access and hydrant distance. See Assistant Fire Marshal document ROS17-00100.
|
1st review completed | | | 4/2/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing - PLAN CHECK | 4/1/2019 | | 4/2/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing - MECHANICAL | 4/1/2019 | | 4/2/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 4/1/2019 | | 4/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/1/2019 | | 4/2/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 4/1/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/1/2019 | | DONE |
|
|
|
|
Application received | | | 3/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 21 2019 8:49AM
|
Routing - PLANNING | 4/1/2019 | | | | FAIL |
|
|
|
I need to see all oa the easesment on the site plan. garage need to be setback from edge of the common drive closest to the house
|