BLD-Final | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | PASS |
Tell Riley
|
|
|
Garage 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover//corrections made//
|
DOC - Permit Finaled | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | NR |
Tell Riley
|
|
|
garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover//need electrical final//
|
BLD-Blower Door Test Results | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | DONE |
Tell Riley
|
|
|
4.7 ACH 50
|
BLD-Energy code compliance | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PASS |
Tell Riley
|
|
|
MARK Phone #: ###-####
|
BLD-Framing/Rough-in | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Tell Riley
|
|
|
MARK Phone #: ###-####
|
BLD-Wall Bracing | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Tell Riley
|
|
|
Mark- Phone #: ###-####3
|
Fees Due Hold | 8/1/2019 | | 8/7/2019 | | DONE |
Judith Amador
|
|
|
|
OVERRIDE | | | 7/31/2019 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/31/2019 | | DONE |
|
|
|
plan mod
|
Telephone call | | | 7/31/2019 | | DONE |
|
|
|
spoke with armada informing the mechanical total should have been 55 not 5 so there is an additional fee of 50 for the manual j modification
|
Fees Due Hold | 7/31/2019 | | 7/31/2019 | | DONE |
Brittany Hill
|
|
|
|
Permit Ready to Issue | | | 7/31/2019 | | DONE |
|
|
|
plan mod for manual J fees due
|
Plan Modification Accepted | | | 7/30/2019 | | DONE |
|
|
|
plan mod-manual J changes only
|
Routing - MECHANICAL | 7/30/2019 | | 7/30/2019 | | PASS |
Troy James
|
|
|
|
BLD-Foundation | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Wall Bracing | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | CANC |
Tell Riley
|
|
|
Mark Phone #: ###-####
|
BLD-Footing | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####//setbacks ok per plans//rebar installed//footings setup per plans//
|
Issue PAID IN FULL permit | | | 6/21/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/21/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/10/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 5/21/2019 | 5/21/2019 | 6/10/2019 | | DONE |
Rob Patrick
|
|
|
06/03 sfd L1 ePlan
|
Routing - PLAN CHECK | 5/21/2019 | | 6/10/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 6/10/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 6/10/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/21/2019 | 5/24/2019 | 5/22/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 5/21/2019 | | 5/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/21/2019 | | 5/22/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - MECHANICAL | 5/21/2019 | | 5/22/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/21/2019 | | 5/21/2019 | | PASS |
Sue Cummings
|
|
|
|
Intake Approval | | | 5/21/2019 | | FAIL |
|
|
|
NEED
Full height of home
Attic access
|
Telephone call | | | 5/21/2019 | | DONE |
|
|
|
spoke with kelly demo of home was done three years ago. stated i will do some more research
|
Plans ACCEPTED BY PLAN TECH | | | 5/21/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/21/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/21/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/20/2019 | | DONE |
|
|
|
emailed kelly to see if the demo is part of this permit or if another company is doing that. went over what needs to be done either way.
|
Application received | | | 5/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 10 2019 4:30PM
|