Permit Information
Permit NumberBLD19-01970
StatusFinaled
Name D & D HANDYMAN SERVICES LLC
Site Address 800 W IDAHO ST Unit: STE 200
Project Name8th Street Entertainment
Customer Number 
ePlanReviewYes
Description
(8TH STREET ENTERTAINMENT – TENANT SPACE EXPANSION) (10-29-19 PLAN MODIFICATION TO PROVIDE RAISED SEATING AREAS ON TWO SIDES OF THE DANCE FLOOR, TO RECONFIGURE A BAR, AND TO REVISE THE OCCUPANT LOAD OF THE TENANT SPACE. EACH RAISED SEATING AREA WILL BE SERVED BY A RAMP. A MULTI-PANEL POCKETING DOOR WILL BE REPLACED WITH AN OVERHEAD DOOR HAVING LAMINATED GLASS.) The fire sprinkler system is used for building area increase, story increase, for fire area, and for fire flow. To expand an existing 4,956 square foot bar (night club) by about 3,781 square feet into adjacent areas on the 2nd story. After the expansion, this tenant space will have a total floor area of about 8,737 square feet. The 2nd story also has a 1,319 square foot storage room that is part of a 1st story tenant space, an 865 square foot common area, and 553 square feet of stairways. Work is to include interior nonbearing walls, an expanded Men’s toilet room accessible to the disabled, a new Women’s toilet room accessible to the disabled, converting an existing toilet room to comply as an assisted-use toilet room, new booth seating, pool tables, dart boards, shuffle board tables, a new pocked folding partition, furniture, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 (including quick-response heads where required) and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 7/14/20208/11/2020 DONE
mailed 8-14-2020 with first letter
Third Notice 5/12/20207/9/2020 DONE
mailed 7-9-2020
Third Notice 4/8/20205/7/2020 DONE
mailed 5-8-2020
Second Notice 3/15/20204/3/2020 DONE
mailed 4-6-2020
First Notice 2/7/20203/5/2020 DONE
mailed 3-6-20
Print Occupancy Form  1/28/2020 DONE
Permanent Occupancy  1/28/2020 DONE
BLD-Final1/24/20201/27/20201/27/2020PPASS
DetailsDave Hannah
DO NOT RESCHEDULE IF NOT GC CALLING Ryan Phone #: ###-####
FIRE-Final Inspection1/24/20201/27/20201/27/2020APASS
DetailsJim Page
Previously noted items have been corrected, fnal life safety inspection complete, permit sign off card not available at time of inspection no signatures provided.


DO NOT RESCHEDULE WITH IF NOT GC CALLING Ryan Phone #: ###-####
CHANGE STATUS TO (ISS)  1/15/2020 DONE
Per Carl W plan modification from 1/10 is no longer going to be done. see email in documents
Plan Reviewer's activity  1/14/2020 DONE
DetailsJoe Bruce
Spoke with RC (Contractor) ###-#### regarding extension of the temporary occupancy. 14 day extension - New expiration date is Jan. 29th.
Plan Modification Accepted  1/10/2020 DONE
various itmes contructed or located differently than permitted drawings indicate
Plan Reviewer's activity  1/7/2020 DONE
DetailsJoe Bruce
Spoke with Steve regarding the name that should be listed on the Certificate of Occupancy. **Karma Nightclub and 8th Street Social Club" which are both operated by 8th Street Entertainment LLC. **JHB**
FIRE-Final Inspection12/31/201912/31/20191/1/2020PPART
DetailsJim Page
Partial final inspection for life fire safety complete. Fire sprinkler inspection is complete, fire alarm inspection is partially complete, reference notes under FIR permit for fire alarms items needed to be completed, fire extinguishers are placed with current inspection tags (Inspection tags on fire extinguishers expires in January). 14 day TCO for life fire safety authorized by Ron Johnson with Boise Fire, permit sign off card not provided at time of inspection.

RC Phone #: ###-####
BLD-Final12/31/201912/31/201912/31/2019PPEND
DetailsDave Hannah
RC Phone #: ###-#### ok for a 15 day tco as per fire
BLD-Conference12/26/201912/27/201912/27/2019ADONE
DetailsDave Hannah
RC Phone #: ###-####
BLD-Conference11/4/201911/5/201911/5/2019ADONE
DetailsDave Hannah
call for access- RC Phone #: ###-####
BLD-Framing/Rough-in10/29/201910/30/201910/30/2019APASS
DetailsDave Hannah
Jake Phone #: ###-####
Plan assigned to (CJW)9/24/20199/24/201910/29/2019 PASS
DetailsCarl Westfall
plan mod for 8th Street Entertainment (at the permits desk)
Routing - PLAN CHECK10/28/2019 10/29/2019 PASS
DetailsCarl Westfall
Plan Reviewer's activity  10/29/2019 PASS
Plan mod review approved
Permit Ready to Issue  10/29/2019 DONE
DO NOT ISSUE -PLAN MOD
NEED
GC and Revised Certificate of Value for the plan mod that was submitted
Telephone call  10/29/2019 DONE
Emailed sent to -rw@chrysalis-architecture.com to get a new value from the plan mod because he did not answer the question on the application. Also, inform him that we would need a 302 and 306
Permit Ready to Issue  10/29/2019 DONE
CHANGE STATUS TO (ISS)  10/29/2019 DONE
Change Expiration Date Only  10/29/2019 DONE
permit was mistakenly re-issued on 10/29/19, corrected issued and expiration date.
Plan Modification Accepted  10/28/2019 DONE
Revised drawings received via Email
BLD-Framing/Rough-in10/21/201910/21/201910/21/2019PPASS
DetailsDave Hannah
Jake Phone #: ###-#### rest rooms walls ok and corrador walls ok
BLD-Framing/Rough-in10/16/201910/17/201910/17/2019APART
DetailsTell Riley
jAKE Phone #: ###-####//ok to cover "Coat storage areas// ok to cover infill walls at corridor//bathroom concealed space will need fire blocking at top and penetrations through floor//add blocking for hand rails//
Plan Modification Accepted  10/17/2019 DONE
Workflow in ePlanReview received
BLD-Framing/Rough-in10/1/201910/2/201910/3/2019APART
DetailsDave Hannah
Jake- inspection for office and green room and girls bathroom Phone #: ###-#### ok to cover green rm and office after elec r/i
Plan Modification Accepted  9/24/2019 DONE
Revise occupant load and provide raised seating with ramp at selected areas around dance floor
Plan Reviewer's activity  9/3/2019 DONE
Removed "Fatty's" from the project description at the request of the owner's consultant.
Telephone call  8/16/2019 DONE
emailed Dan Denning Wed and today Friday to sign the 302 form.
8/16/19-done
Issue PAID IN FULL permit  8/13/2019 DONE
Print Occupancy Form  8/13/2019 DONE
CHANGE ISSUED DATE  8/13/2019 DONE
permit was mistakenly re-issued on 10/29/19, corrected issued and expiration date.
Telephone call  8/5/2019 DONE
Received 302 & 306 via fax. GC form ok, but electrical value $0 on 306. Need to re-fax cert of value to provide electrical value and include electrical value in overall project value.
Plan assigned to (CJW)6/13/20197/9/20197/30/2019 PASS
DetailsCarl Westfall
(1st done) 07/02/19 (L-3 - 15 days) (eplan - 19 sheets) Fatty's Bar (back to applicant)
Routing - PLAN CHECK7/29/2019 7/30/2019 PASS
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  7/30/2019 DONE
Permit Ready to Issue  7/30/2019 DONE
DetailsCandy A. Nichols
all met-emailed ddservices.denning@gmail.com the fees due--Need rev cert of val-met

Need GC-met
Plan resubmittals received  7/29/2019 DONE
Routing - PLAN CHECK7/24/2019 7/25/2019 FAIL
DetailsCarl Westfall
Resubmittal required - remember to upload the plan review report
Plan resubmittals requested  7/25/2019 DONE
Plan resubmittals received  7/24/2019 DONE
Route to Impact Fee Review7/10/20197/13/20197/11/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing PW Environmental6/17/2019 7/10/2019 PASS
DetailsRick Christenson
Plan resubmittals requested  7/10/2019 DONE
Routing - FIRE6/13/20196/13/20197/9/2019 PASS
DetailsMark Scharfen
07.09.2019-Completed fire reveiw. Uploaded rev_fire 07.09.2019.pdf.
1st review completed  7/9/2019 DONE
Routing - PLAN CHECK6/13/2019 6/28/2019 FAIL
DetailsCarl Westfall
Routing - MECHANICAL6/13/2019 6/27/2019 PASS
DetailsTroy James
Routing - PLUMBING6/13/2019 6/17/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - PUBLIC WORKS6/13/2019 6/17/2019 PASS
DetailsMorgan Webb
Routing - Addressing6/13/2019 6/14/2019 PASS
DetailsDoug Chausow
Intake Approval  6/12/2019 PASS
DetailsJoe Bruce
Prescreen approved by JHB.
Intake Approval  6/5/2019 FAIL
DetailsJoe Bruce
Provide the following items to complete the prescreen process:
1) Plan sheets G1-3, G1-6, and G1-7 do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp.
2) Provide a door schedule and hardware schedule for the new doors shown on the floorplan.
3) Provide locations of exit signs and emergency lighting locations on the plan.
4) Provide portable fire extinguisher locations on the floor plan.
5) Provide fire resistive assembly details for penetrations at existing 1-hour rated floor assembly.
6) Provide structural calculations stamped and signed by and Idaho licensed engineer for the increased floor loading of this assembly occupancy.
7) Provide structural plans as required by the checklist if required by increased floor load.
Application received  5/30/2019 DONE
Application submitted via PDS Online on May 30 2019 12:51PM
Plan assigned to (CJW)1/10/20201/10/20201/16/2019 DONE
DetailsCarl Westfall