Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-02032
StatusFinaled
Name DOUG LASHER CONSTRUCTION
Site Address 3492 E HEARTLEAF DR
Project Name 
Customer Number 
ePlanReviewNo
Description
**HILLSIDE** **WUI VALLEY ZONE B REQUIREMENTS** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 5333 sq. ft., two story (first story 4120 sq. ft., second story 1213 sq. ft.) single family dwelling with 3 bedrooms, 3 bathrooms, 2 half bathrooms, approximately 160 sq. ft. of covered patio/porch and a 1290 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. JJNA letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final. ***SPRINKLERS ARE NOT REQUIRED*** LGM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/3/20203/3/20203/3/2020PPASS
DetailsJim Storey
Front door unlocked Phone #: ###-#### Inspection requested via web by bryan murdoch
DOC - Permit Finaled3/3/20203/3/20203/3/2020PPASS
DetailsJim Storey
BLD-Final2/26/20202/26/20202/26/2020ANR
DetailsJim Storey
Garage code is 1905 thanks Phone #: ###-#### Inspection requested via web by bryan murdoch handrail clearance/ pool cover
PubWorks Occupancy Approval2/24/20202/24/20202/24/2020 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.

BLD-Energy code compliance11/8/201911/8/201911/8/2019PPASS
DetailsJim Storey
Happy Friday thanks Phone #: ###-#### Inspection requested via web by bryan murdoch
BLD-Framing/Rough-in11/5/201911/5/201911/5/2019APASS
DetailsJim Storey
Thanks Phone #: ###-#### Inspection requested via web by bryan murdoch
Routing - MECHANICAL10/28/2019 10/28/2019 PASS
DetailsTroy James
Revised manual j report
BLD-Wall Bracing9/25/20199/25/20199/25/2019PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by bryan murdoch
BLD-Foundation7/11/20197/11/20197/11/2019PPASS
DetailsJim Storey
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing7/10/20197/10/20197/11/2019PPASS
DetailsJim Storey
Thanks Phone #: ###-#### Inspection requested via web by bryan murdoch
BLD-Footing7/8/20197/9/20197/9/2019ANR
DetailsJim Storey
Phone #: 2086971241 >> Inspection requested via mobile web by Heron need pw sign off
BLD-Footing7/9/20197/9/20197/9/2019PNR
DetailsJim Storey
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
PubWorks Subgrade Approval7/9/20197/9/20197/9/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Issue PAID IN FULL permit  7/2/2019 DONE
Inspection Record Card- Bld  7/2/2019 DONE
OVERRIDE  7/1/2019  
Routing - FIRE6/24/20196/24/20197/1/2019 PASS
DetailsLee G Meredith
07/01-3492 E Heartleaf Dr. paper resubmittal-LGM

Sprinklers are not required.
Plan assigned to (J_N)6/6/20196/6/20197/1/2019 DONE
DetailsJenny Nelson
06/25 sfd L2 Paper - with BLD19-02081 (pool). 1st complete 6/24, failed hillside and fire.
Case Summary (BLD)  7/1/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  7/1/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  7/1/2019 DONE
MET
Inspection Record Card- Bld  7/1/2019 DONE
Telephone call  7/1/2019 DONE
Left voicemail to inform Doug that the permit is ready and what fees are due.
Routing - PUBLIC WORKS6/28/2019 6/28/2019 PASS
DetailsMorgan Webb
Routing PW Grading-Hillside6/24/2019 6/28/2019 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Routing - FIRE6/6/20196/6/20196/25/2019 FAIL
DetailsLee G Meredith
06/20-2492 E Heartleaf Dr. RES Paper 404.

Inadequate fire flow.
1st review completed  6/24/2019 DONE
DetailsJenny Nelson
Routing - PLAN CHECK  6/24/2019 PASS
DetailsJenny Nelson
Routing - PLANNING6/6/2019 6/24/2019 PASS
DetailsLeon Letson
Plan resubmittals requested  6/14/2019 DONE
Three copies each of Structural Calculations stamped and taken to plan reviewer.
Routing - Erosion and Sediment6/13/2019 6/13/2019 PASS
DetailsAndy J. Long
ESC plan approved. Site preparation inspection is required.
Routing PW Grading-Hillside6/13/2019 6/13/2019 FAIL
DetailsMelissa Jannusch
retaining wall calcs
Routing - MECHANICAL  6/13/2019 PASS
DetailsTroy James
Route to Impact Fee Review6/6/20196/9/20196/7/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Plans ACCEPTED BY PLAN TECH  6/6/2019 DONE
Intake Approval  6/6/2019 PASS
Recd Pcfee & Taken To Pln CK  6/6/2019 DONE
Routing - Addressing6/5/2019 6/5/2019 PASS
DetailsDoug Chausow
Application received 6/4/2019   
Routing - PUBLIC WORKS6/6/2019   FAIL
DetailsMorgan Webb