(THE ASPEN – EAST STAIRWELL WATER DAMAGE REPAIR) ""PREINSPECTION IS REQUIRED PRIOR TO THE START OF ANY WORK"" Permit for repairs to an existing commercial and residential high-rise building resulting from rain/snow water damage with work to include nonstructural work consisting of select repair and replacement of damaged walls from the basement through the 17th floors east stairwell of the building as noted on the plans provided. All work is required to be completed per the original approved plans with no modifications without prior approval and resubmittal of plans. All rated assemblies are to be reconstructed per the original approved plans. JG
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection6/26/20206/26/20206/30/2020 PEND
DetailsDave Hannah
BLD-Aging Inspection6/25/20206/25/20206/30/2020 PEND
DetailsDave Hannah
BLD-Energy code compliance2/11/20202/11/20202/12/2020PPASS
DetailsDave Hannah
Ken Phone #: ###-#### first layer of sheetrock ok
BLD-Energy code compliance2/4/20202/5/20202/5/2020APASS
DetailsDave Hannah
Ken- please call for access Phone #: ###-####
BLD-Conference9/26/201910/2/201910/2/2019APASS
DetailsDave Hannah
on stairwells Phone .. call Tony,, ###-####
BLD-Conference9/25/20199/26/20199/26/2019PPEND
DetailsTony Young
on stairwells Phone #: ###-####-pleae call when on way for access and to meet/// stairwells are compromised due to double layer of sheetrock being cut out to dry behind,, called plan review so they could let fire know
BLD-Conference9/25/20199/26/20199/26/2019PPEND
DetailsTony Young
on stairwells Phone #: ###-####,, water issues,, opened drywall up,, coming from magor rain storm events,, can add thresh holds up to 1/2"
BLD-Conference9/25/20199/25/20199/25/2019PCANC
DetailsJim Storey
on stairwells Phone #: ###-####
Issue PAID IN FULL permit  6/18/2019 DONE
Plan assigned to (JG)6/11/2019 6/17/2019 PASS
DetailsJavier Guzman
06/17 L1 ASPEN LOFTS LLC Stairway repair paper
Routing - PLAN CHECK6/11/2019 6/17/2019 PASS
DetailsJavier Guzman
1st review completed  6/17/2019 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  6/17/2019 DONE
Case Summary (BLD)  6/17/2019 DONE
Permit Ready to Issue  6/17/2019 DONE
Met
Inspection Record Card- Bld  6/17/2019 DONE
Telephone call  6/17/2019 DONE
Spoke with Ken to inform him the permit is ready and what fees are due.
Plans ACCEPTED BY PLAN TECH  6/11/2019 DONE
Recd Pcfee & Taken To Pln CK  6/11/2019 DONE
Intake Approval  6/11/2019 PASS
Application received 6/11/2019