Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberBLD19-02217
StatusIssued
Name FOREGGER DANIEL J
Site Address 1024 W HAYS ST
Project NameForegger foray
Customer Number 
ePlanReviewNo
Description
FRAMING MAY BEGIN ON HOUSE - DEFERRED SUBMITTALS STILL REQUIRED FOR DECK AND GARAGE - PERMIT FOR A MAJOR REMODEL THAT ADDS 1,690SQ' OF BASEMENT, 302SQ' TO THE MAIN LEVEL, AND 1,015SQ' TO THE UPPER LEVEL. FINAL HOME IS 5BD/4BTH. 11-15-19 **jab**+ Permit for any demo needed to expose the structure in advance of final drawings and engineering. No framing allowed under this permit. Applicant may begin concrete work "At Own Risk". Any construction not in compliance with the code or later plans/engineering are the owner’s responsibility and shall be corrected at the owner's expense. The foundation is required to be placed per the approved site plan. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall Bracing6/9/20206/10/20206/10/2020APASS
DetailsTony Young
shear... screened // Mark Phone #: ###-####/
see paint,, fix// then ok
BLD-Foundation3/13/20203/16/20203/16/2020APASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing2/20/20202/21/20202/21/2020APASS
DetailsDave Hannah
Jack Phone #: ###-####
BLD-Foundation2/19/20202/20/20202/20/2020PPART
DetailsTony Young
Jack Phone #: ###-####.. work in progress on basement footings on new area
BLD-Foundation11/22/201911/22/201911/22/2019PPART
DetailsMike Jordan
Jack Phone #: ###-####. Basement walls, portion under original house only.
CHANGE STATUS TO (ISS)  11/21/2019 DONE
OVERRIDE  11/18/2019  
Plan assigned to (JAB) Josh8/28/20198/28/201911/18/2019 PASS
DetailsJosh Bogle
08/30 mdification, paper - 1st done
Telephone call  11/18/2019 DONE
left a message for daniel informing him the plan mod is ready and the fee amount due
Permit Ready to Issue  11/18/2019 DONE
PLAN MOD
Routing - PLAN CHECK11/15/2019 11/15/2019 PASS
DetailsJosh Bogle
house only - not garage or decks
Inspection Record Card- Bld  11/15/2019 DONE
DetailsJosh Bogle
Case Summary (BLD)  11/15/2019 DONE
DetailsJosh Bogle
Plan resubmittals received  11/14/2019 DONE
two copies of sheets a2.3, a3.3, a3.5, and s1.0 taken to josh b
BLD-Foundation11/8/201911/12/201911/12/2019APASS
DetailsDave Hannah
Jack Phone #: ###-#### front half ok
Routing - PLAN CHECK9/26/2019 9/26/2019 FAIL
DetailsJosh Bogle
1.5hrs review time - see e-mail to Daniel
Plan resubmittals received  9/18/2019 DONE
resubmittals for plan mod. Two copies each of garage plans in smaller size plans and large plans for house addition stamped and taken to plan reviewer.
Routing - PLAN CHECK9/5/2019 9/5/2019 FAIL
DetailsJosh Bogle
3hrs review time - see e-mail to Daniel
Plan Modification Accepted  8/26/2019 DONE
PLAN MOD-this is like a phase 2 after the demo work. Submitted 2 of everything-gave to JAB
OVERRIDE  8/9/2019  
Issue PAID IN FULL permit  8/9/2019 DONE
Permit Ready to Issue  8/9/2019 DONE
Plan assigned to (JAB) Josh6/17/20196/17/20198/8/2019 PASS
DetailsJosh Bogle
06/21 remodel, paper - 1st done
Routing - PLAN CHECK8/8/2019 8/8/2019 PASS
DetailsJosh Bogle
issuance of "At Own Risk" concrete and demo permit
Inspection Record Card- Bld  8/8/2019 DONE
DetailsJosh Bogle
Case Summary (BLD)  8/8/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  8/8/2019 DONE
DetailsJosh Bogle
ESC yes - Energy no
Plan resubmittals received  8/2/2019 DONE
Two copies of sheets A-0.0, A-0.1, A-0.2, A-0.3, A-2.0, A-2.0F, A-2.1, A-2.1F, A-2.2, A-2.3, A-3.1, A-3.2, A-4.1, A-4.2, A-4.3, A-6.0, A-6.1, A-6.2, A-7.0, A-7.1, A-7.2, A-9.1 and A-55 taken to josh
Garage (two small sets) A0.0, A0.1, A0.2, A0.3, A0.4, A0.4.5, A0.5, A0.6, A0.7, A0.8, A0.9, A0.10, A0.11 and A0.12 taken to josh
Routing - PLAN CHECK8/2/2019 8/2/2019 FAIL
DetailsJosh Bogle
see e-mail to Daniel
Routing - PLAN CHECK6/21/2019 6/24/2019 FAIL
DetailsJosh Bogle
see e-mail to Daniel
1st review completed  6/24/2019 FAIL
DetailsJosh Bogle
Routing - MECHANICAL6/17/2019 6/21/2019 PASS
DetailsTroy James
Routing - PLANNING6/17/2019 6/17/2019 PASS
DetailsKayCee Babb
Per DRH19-00091. To comply with all Conditions of Approval.
Intake Approval  6/17/2019 PASS
Recd Pcfee & Taken To Pln CK  6/17/2019 DONE
no fees paid at intake
Application received 6/14/2019