Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-02502
StatusIssued
Name CLEARWATER LANDSCAPE AND IRRIGATION
Site Address 2675 N SHAMROCK AVE
Project NameUstick Placemaking Project
Customer Number 
ePlanReviewYes
Description
SPECIAL INSPECTIONS REQUIRED- Permit to construct a 10'x30' (300 sq ft) cantilevered, steel covering and related site improvements. Scope of work includes (3) conc. foundation piers as per engineering, (3) steel columns supporting an engineered cantilevered covering, adding an accessible route, new pavers and bench seating to existing Redwood Neighborhood park. Note: Special Inspections Required see form 310. All work shall comply with the approved plans and all applicable codes. ***BJM***
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection3/26/20203/26/20203/26/2020 PEND
DetailsTell Riley
BLD-Footing11/12/201911/13/201911/13/2019PPART
DetailsTell Riley
Concrete schedule to show up at 4 P.M tomorrow. Phone #: ###-#### Inspection requested via web by David Snow//ok pending specials//
BLD-Footing10/25/201910/28/201910/28/2019APART
DetailsTell Riley
Plans will be available on site. Call number if there''s any problem finding them.

Thanks,
Phone #: ###-#### Inspection requested via web by David Snow//will need cold weather protection//no frost present at this time//special inspections will need to be completed per approved plans and engineering//
BLD-Footing10/23/201910/24/201910/24/2019ANR
DetailsTell Riley
Inspection for three building footings. vary in depths Phone #: ###-#### Inspection requested via web by David Snow//need plans and engineering onsite//talekd with David he will get them here and call in for re-inspection//
Meeting  10/21/2019 DONE
Emailed a reminder to David to please print and sign his name on the building permit and email it back to me.
Issue PAID IN FULL permit  10/15/2019 DONE
Inspection Record Card- Bld  10/15/2019 DONE
Telephone call  10/14/2019 DONE
Emailed GC to inform him not all the fees were paid for this project. Once the remaining fees are paid we can issue the permit.
Telephone call  10/11/2019 DONE
emailed applicant to let them know that we still need an RP before we can issue this permit
OVERRIDE  10/8/2019  
Plan assigned to (BJM)8/2/20198/2/201910/8/2019 DONE
DetailsBrian McGowan
2nd Review Complete- 502 Ustick Placemaking Project Shelter
Routing Off Site - STRUCTURAL10/7/2019 10/8/2019 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  10/8/2019 DONE
DetailsBrian McGowan
Permit Ready to Issue  10/8/2019 DONE
all met:
Need GC form
Need RP
Routing - PLAN CHECK10/7/2019 10/7/2019 PASS
DetailsBrian McGowan
Routing Off Site - STRUCTURAL9/27/2019 10/3/2019 FAIL
DetailsBrian McGowan
Did not resolve the signature issues
Routing - PLAN CHECK9/27/2019 10/3/2019 FAIL
DetailsBrian McGowan
Did not resolve issues.
Routing - FIRE8/2/20198/2/20199/19/2019 PASS
DetailsMark Scharfen
No comments attached. U occupancy. Hydrants, fire flow and FD access okay.
1st review completed  9/19/2019 FAIL
DetailsBrian McGowan
Routing - PLAN CHECK8/2/2019 9/18/2019 FAIL
DetailsBrian McGowan
Routing PW Drainage8/2/2019 8/21/2019 PASS
DetailsBrian Murphy
Routing PW Street Lights8/2/2019 8/5/2019 PASS
DetailsTom Marshall
Routing - PLANNING8/2/2019 8/5/2019 PASS
DetailsNicolette Womack
Routing - Addressing8/2/2019 8/5/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/2/2019 8/2/2019 PASS
DetailsAngela Hardy
Routing - Erosion and Sediment8/2/2019 8/2/2019 PASS
DetailsMichael Zawacki
Waiver approved.
Intake Approval  8/2/2019  
DetailsBrian McGowan
Intake Approval  7/24/2019 FAIL
DetailsBrian McGowan
Please provide the following in order to process your Prescreen:

1. No Soils Report was provided. ( Engineering calculations must be set at default values if no Soils Report is provided).
2. No Planning and Zoning Approval letters were provided.
3. The (3) sheets of the Shelter Certified Drawings must be uploaded individually and renamed exactly as the Drawing they are intended to replace. This will Version over the existing drawing and give it a designation of V2.
4. Drawings L-100 and T-100 must be rotated. Rename them exactly as the Drawing they are intended to replace.
Intake Approval  7/22/2019 FAIL
DetailsBrian McGowan
Please provide the following in order to process your Prescreen:

1. No Soils Report was provided.
2. No Lot Verification form was provided. This must be a form signed by a City of Boise Planner.
3. No Planning and Zoning Approval letters were provided.
4. The (3) sheets of the Shelter Certified Drawings are not stamped by the Engineer. These stamps and signature must be relocated on the drawings since they are now in the area the City Approval Stamp will be placed.
5. Sheets L100 and T100 have information where the City Approval Stamp will be located. Please relocate that information to a different area on the Sheet.
6. The Site Plan will work but needs to be uploaded into the drawing file and oriented properly.
7. The Checklist must note what Sheet the information can be found on. We do not have time to search the sheets for the information.
Intake Approval  7/16/2019 FAIL
DetailsBrian McGowan
Please provide the following in order to process your Prescreen:
1. Form #310 must have the Owner and Design Professional filled in and signed.
2. No structural engineering calculations were provided.
3. No Soils Report was provided.
4. No Lot Verification form was provided.
5. No Planning and Zoning Approval letters were provided.
6. The (3) sheets of the Shelter Certified Drawings are not stamped by the Engineer. These stamps and signature must be relocated on the drawings since they are now in the area the City Approval Stamp will be placed.
7. Sheets L100 and T100 have information where the City Approval Stamp will be located. Please relocate that information to a different area on the Sheet.
8. Provide a Site Plan showing the location of the Shelter on the parcel with dimensions to property lines.
9. The Checklist must note what Sheet the information can be found on. We do not have time to search the sheets for the information.
Intake Approval  7/10/2019 FAIL
DetailsMichael Hanson
Returning for applicant to upload additional documents
1. Construction drawings must be individually uploaded
Intake Approval  7/9/2019 FAIL
DetailsMichael Hanson
Missing 310 form for infield welding and structural bolting.
Missing 304 form.
Missing 502 checklist
Applicant is looking to apply online
Application received  7/8/2019 DONE
Application submitted via PDS Online on Jul 8 2019 4:21PM
Routing Off Site - STRUCTURAL8/2/2019   FAIL
DetailsBrian McGowan
AHJ- Corresctions Required