BLD-Final | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | NR |
Tony Young
|
|
|
screened - there have been school employees inside // Mike Phone #: ###-####
|
FIRE-Final Inspection | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Jim Page
|
|
|
Door hardware complies with 2015 IFC section 1010.1.9.9 with push button and motion sensor accessories. Final life fire safety inspection for scope of work is complete.
screened - there have been school employees inside // Mike Phone #: ###-####
|
BLD-Aging Inspection | 8/7/2020 | 8/7/2020 | 8/13/2020 | | PEND |
Tony Young
|
|
|
|
FIRE-Conference | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | DONE |
Troy Cobbley
|
|
|
Need to submit the door hardware for plan review approval as discussed. It appears sprinklers and alarm is ok.
Mike ***Cleared*** Phone #: ###-####
|
BLD-Foundation | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | CANC |
Mike Jordan
|
|
|
wall // mike Phone #: ###-####
|
BLD-Framing/Rough-in | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | PART |
Mike Jordan
|
|
|
wall // mike Phone #: ###-####. Needs to remove screws from grid and provide kickers to structure. Ok to cover. will verfiy kickers install at final by removing ceiling grid. Also went over mag lock details with contractor.
|
Issue PAID IN FULL permit | | | 10/30/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/28/2019 | | DONE |
|
|
|
MET DEREK@RRCCONTRACTORS.COM
NEED
GC
Revised Certificate of Value
|
Plan assigned to (BJM) | 9/10/2019 | 9/10/2019 | 10/25/2019 | | DONE |
Brian McGowan
|
|
|
10/25- 1st Review Complete- L2 RHPCS Door Addition ePlan
|
Routing - PLAN CHECK | 10/25/2019 | | 10/25/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/25/2019 | | DONE |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 10/23/2019 | 10/26/2019 | 10/24/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 9/10/2019 | | 10/23/2019 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 10/23/2019 | | FAIL |
Brian McGowan
|
|
|
|
Intake Approval | | | 9/9/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 7/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 11 2019 2:41PM
|