Permit Information
Permit NumberBLD19-02587
StatusIssued
Name KEARNS WILLIAM J
Site Address 124 E CURLING DR
Project NameKearns Deck
Customer Number 
ePlanReviewNo
Description
*PLAN MODIFICATION - changing roof over entry way - engineering provded JJN 08/22/19** CAT I Hillside Permit for a remodel, to include: Exterior deck expansion, new sliding doors on exterior of main level, and reconfiguring roof. - All work per plans, notations, attachments, engineering, local codes & ordinances. JJN
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/20/20202/20/20202/21/2020 PEND
DetailsTony Young
BLD-Aging Inspection2/19/20202/19/20202/20/2020 PEND
DetailsTony Young
BLD-Framing/Rough-in10/7/201910/8/201910/8/2019PPASS
DetailsTony Young
Dion Phone #: ###-####// decks and entry ok
BLD-Energy code compliance10/3/201910/4/201910/4/2019APASS
DetailsJim Storey
Dan Phone #: ###-####
BLD-Framing/Rough-in10/1/201910/2/201910/2/2019APASS
DetailsTony Young
Dan Phone #: ###-####,, ok to insulate
PubWorks Subgrade Approval9/4/20199/4/20199/4/2019 DONE
DetailsMelissa Jannusch
*REMAINING FOUR FOOTINGS* A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
BLD-Footing8/30/20199/3/20199/3/2019APART
DetailsTony Young
Dion Phone #: ###-####,, new post footings ok
PubWorks Subgrade Approval9/3/20199/3/20199/3/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Plan Modification Accepted  8/22/2019 DONE
DetailsJenny Nelson
Changing roof over entry
Routing - PLAN CHECK8/22/2019 8/22/2019 PASS
DetailsJenny Nelson
1 hour Plan mod fee
Case Summary (BLD)  8/22/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  8/22/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  8/22/2019 DONE
CHANGE STATUS TO (ISS)  8/22/2019 DONE
BLD-Footing8/16/20198/20/20198/21/2019PNR
DetailsBrandon Shaw
Need soil subgrade submitted and approved by PW...
BLD-Conference8/5/20198/6/20198/6/2019APART
DetailsTony Young
Dion Phone #: ###-####,, needs reviewed plans,, any changes need to be gone through the engineer of record,, also approved by the fire for soffits changes
Issue PAID IN FULL permit  7/24/2019 DONE
Plan assigned to (J_N)7/12/20197/12/20197/23/2019 DONE
DetailsJenny Nelson
07/18 Hillside deck addition, 1st review 7/22, had to wait on hillside. need timber compliant with wui zone, soffit vent, special inspections, cable rail and spray foam
Routing - PLAN CHECK7/23/2019 7/23/2019 PASS
DetailsJenny Nelson
Inspection Record Card- Bld  7/23/2019 DONE
DetailsJenny Nelson
Case Summary (BLD)  7/23/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  7/23/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  7/23/2019 DONE
met
Telephone call  7/23/2019 DONE
Spoke with William to inform him the permit is ready and what fees are due.
Meeting  7/23/2019 DONE
Spoke with Andy L, No ESC needed.
Routing - PLAN CHECK7/22/2019 7/22/2019 FAIL
DetailsJenny Nelson
Wui zone timber, cable rail engineering, special inspections, soffit vent
Routing PW Grading-Hillside7/12/2019 7/22/2019 PASS
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
1st review completed  7/22/2019 DONE
DetailsJenny Nelson
Routing Walk-In (Zoning)7/12/20197/12/20197/12/2019PPASS
DetailsKarla Nelson
Applicant spoke with Jason and a Hillside permit is not needed.
Routing Walk-In (BLD)7/12/20197/12/20197/12/2019PFAIL
DetailsJenny Nelson
took in as level 2 for hillside
Application received 7/12/2019