Temporary Occupancy | 7/2/2020 | 9/30/2020 | 7/2/2020 | | DONE |
Brittany Hill
|
|
|
|
Zoning Approval | 7/1/2020 | 7/1/2020 | 7/1/2020 | | DONE |
Leon Letson
|
|
|
TEMP see email in docs blh 7-2-2020
|
Fees Due Hold | 6/24/2020 | | 6/30/2020 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 6/30/2020 | 6/30/2020 | 6/30/2020 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, final life fire safety inspection is complete.
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Final | 6/22/2020 | 6/23/2020 | 6/23/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson/ ok pending zoning and others
|
FIRE-Final Inspection | 6/22/2020 | 6/23/2020 | 6/23/2020 | P | FAIL |
Jim Page
|
|
|
Correctly repair holes that were next to fire sprinkler heads in furnace closets.
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Final | 6/17/2020 | 6/18/2020 | 6/23/2020 | P | NR |
Tony Young
|
|
|
please call 30 minutes before inspection Phone #: ###-#### Inspection requested via web by bill gullickson
|
FIRE-Final Inspection | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | CANC |
Jim Page
|
|
|
Duplicate inspection request, this request is cancelled.
please call 30 minutes before inspection Phone #: ###-#### Inspection requested via web by bill gullickson
|
FIRE-Final Inspection | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | CANC |
Jim Page
|
|
|
Duplicate inspection request, this request is cancelled.
please call 30 minutes before inspection Phone #: ###-#### Inspection requested via web by bill gullickson
|
FIRE-Final Inspection | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | FAIL |
Jim Page
|
|
|
Riser room is not 1 hour rated as required under BMC 7-01-51. Provide apartment numbers instead of apartment letters as specified under the Building Permit Fire Code Review Comments section 12A. Sprinkler escutcheon needs to cover entire sprinkler hole penetration, furnace rooms in apartments labeled A, C and D at time of inspection had large gaps between sheetrock and edge of escutcheon.
Hard wire riser room heaters instead of plug in as discussed. please call 30 minutes before inspection Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Footing | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | NR |
Tell Riley
|
|
|
Gazebo inspection - Lynda Phone #: ###-####//plans show Gazebo is not part of the permit//let onsite contact know//no plans for gazebo onsite--cannot find permit associated with gazebo//will re-schedule when permit is obtained//
|
BLD-Wall Bracing | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson// exterior was ok to cover
|
BLD-Energy code compliance | 3/9/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Tony Young
|
|
|
Insulation inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Framing/Rough-in | 3/5/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Tony Young
|
|
|
Framing inspection. Please call Nic a half hour before inspection. Cheers, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
CHANGE STATUS TO (ISS) | | | 2/19/2020 | | DONE |
|
|
|
plan mod approved
|
BLD-Wall Bracing | 2/14/2020 | 2/18/2020 | 2/18/2020 | A | CANC |
Tony Young
|
|
|
Ed Phone #: ###-#### Inspection cancelled from web by: Nic Van Diepen
|
Plan assigned to (JG) | 2/7/2020 | 2/7/2020 | 2/18/2020 | | PASS |
Javier Guzman
|
|
|
02/18 plan mod Eaglehawk Fourplex - Bldg 4
|
Routing - PLAN CHECK | 2/12/2020 | | 2/18/2020 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 2/18/2020 | | DONE |
|
|
|
**PLAN MOD - DO NOT REISSUE** All plan mod fees assessed on BLD19-02617
|
Routing - MECHANICAL | 2/12/2020 | | 2/12/2020 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 2/7/2020 | | DONE |
|
|
|
plan mod 1
|
BLD-Framing/Rough-in | 1/24/2020 | 1/24/2020 | 1/24/2020 | P | PART |
Tony Young
|
|
|
Exterior osb shear inspection. Please call Nic a half hour before inspection. Cheers, Phone #: ###-#### Inspection requested via web by Nic Van Diepen// exterior ok to cover
|
BLD-Wall cover | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Tony Young
|
|
|
Party wall truss GWB shear inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Concrete | 12/13/2019 | 12/13/2019 | 12/13/2019 | A | PASS |
Tony Young
|
|
|
Building interior slab on grade. Concrete at 9:30am. Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Energy code compliance | 11/22/2019 | 11/22/2019 | 11/25/2019 | P | PASS |
Tony Young
|
|
|
Foundation rigid Insulation inspection. Thanks! Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Footing | 11/12/2019 | 11/13/2019 | 11/13/2019 | P | PASS |
Tony Young
|
|
|
Pat Phone #: ###-####
|
Fees Due Hold | 10/5/2019 | | 11/12/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Telephone call | | | 10/4/2019 | | DONE |
|
|
|
called Perryman-talked to
Addy in accounting-she will let the GC know that there are more fees due-i told her they wouldn't be able to schedule and inspection untill it was paid
|
Issue PAID IN FULL permit | | | 9/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/19/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/18/2019 | | |
|
|
|
|
Plan assigned to (JG) | 7/17/2019 | 7/18/2019 | 9/18/2019 | | PASS |
Javier Guzman
|
|
|
9/20 3rd rev comp, 08/27 - 506 Eaglehawk Fourplex Bldg 4
|
Routing PW Sewer Design | 9/18/2019 | | 9/18/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 9/18/2019 | | 9/18/2019 | | PASS |
Evan Carpenter
|
|
|
signed off in ePlan by PW Solid Waste Evan Carpenter
|
Routing - PLAN CHECK | 9/16/2019 | | 9/18/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Street Lights | 9/16/2019 | | 9/18/2019 | | PASS |
Tom Marshall
|
|
|
signed off in ePlan by PW Street Lights Tom Marshall
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/18/2019 | | DONE |
|
|
|
Need
ACHD
GC Form
Revised Value
DO NOT ISSUE WITHOUT BLD19-02617-BLD19-02622
|
Routing - Design Review | 9/16/2019 | | 9/17/2019 | | PASS |
Josh Wilson
|
|
|
Revised site and landscape plan ok
|
Routing - PLAN CHECK | 9/3/2019 | | 9/11/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 9/3/2019 | | 9/11/2019 | | PASS |
Troy James
|
|
|
Signed off in ePlan by Troy James
|
Routing Off Site - STRUCTURAL | 9/3/2019 | | 9/11/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by KPFF Engineer
|
Routing PW Drainage | 9/3/2019 | | 9/11/2019 | | PASS |
Melissa Jannusch
|
|
|
Drainage approved under the subdivison review process ODI 3719
|
Routing PW Street Lights | 9/3/2019 | | 9/11/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 9/10/2019 | | 9/11/2019 | | PASS |
Leon Letson
|
|
|
signed off in ePlan Planning Leon Letson
|
Routing - FIRE | 9/3/2019 | 9/3/2019 | 9/10/2019 | | PASS |
Mark Scharfen
|
|
|
09/10-Eaglehawk building 4 resubmittal. Fire review complete. Uploaded rev_fire 09.10.2019.pdf
|
Routing - Design Review | 9/3/2019 | | 9/10/2019 | | FAIL |
Josh Wilson
|
|
|
|
Meeting | | | 8/22/2019 | | DONE |
|
|
|
after talking with Doug in addressing-all addresses started as 7485 N Lucy Rose Ln. When the parcel and addresses changed no one changed them so I am doing now. He said to go with what GIS shows. Use the parcel with the correct address.
|
Route to Impact Fee Review | 8/20/2019 | 8/23/2019 | 8/21/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/17/2019 | 7/18/2019 | 8/20/2019 | | FAIL |
Mark Scharfen
|
|
|
08/20-Eaglehawk Fourplex Bldg 4 review completed. Uploaded rev_fire 08.20.2019.pdf and emailed to architect.
|
Routing Off Site - STRUCTURAL | 7/17/2019 | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by KPFF Engineer
|
Routing PW Street Lights | 7/19/2019 | | 8/20/2019 | | FAIL |
Tom Marshall
|
|
|
Failed in ePlan by PW Street Lights Tom Marshall
|
Routing PW Sewer Design | 7/19/2019 | | 8/20/2019 | | FAIL |
DeAnn Brown
|
|
|
Failed in ePlan by PW Sewer Design DeAnn Brown
|
Routing PW Solid Waste | 7/19/2019 | | 8/20/2019 | | FAIL |
Evan Carpenter
|
|
|
Failed in ePlan by PW Solid Waste Evan Carpenter
|
1st review completed | | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 7/17/2019 | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Drainage | 7/19/2019 | | 7/29/2019 | | FAIL |
Melissa Jannusch
|
|
|
Please provide most recent set of Civil Plan dated 10-1-2018
|
Routing - MECHANICAL | 7/17/2019 | | 7/24/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to Architect
|
Routing - Erosion and Sediment | 7/17/2019 | | 7/23/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid RP. Site preparation inspection required.
|
Routing - PLANNING | 7/17/2019 | | 7/21/2019 | | PASS |
Leon Letson
|
|
|
|
Routing - PUBLIC WORKS | 7/17/2019 | | 7/19/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 7/17/2019 | | 7/18/2019 | | PASS |
Doug Chausow
|
|
|
Correct address: 7356 N Lucy Rose Ln
|
Routing - PLUMBING | 7/17/2019 | | 7/18/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 7/17/2019 | | PASS |
Brian McGowan
|
|
|
|
Application received | | | 7/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 15 2019 2:09PM
|
Routing - Design Review | 7/17/2019 | | | | FAIL |
Andrea Tuning
|
|
|
Locate the street trees along Bogart Lane within the landscape planter located between the sidewalk and the curb line.
Install landscape planter islands at the terminus of each row of parking. The planters shall be a minimum of 8-feet in width (measured inside of curb to inside of curb) and include the required Class II or Class III tree with low shrubs or other vegetative groundcover.
Install a mixture of deciduous and evergreen trees, shrubs, or other vegetative groundcover in the northwest corner of the site that will create a visual barrier that provides a minimum of 60-percent of a barrier within five years of planting for the existing single-family residential dwelling that is an “out parcel”.
Locate all site lighting outside of the required planter islands.
Clearly identify all mechanical units and how they will be screened.
|