Temporary Occupancy | 7/2/2020 | 9/30/2020 | 7/2/2020 | | DONE |
Brittany Hill
|
|
|
|
Zoning Approval | 7/1/2020 | 7/1/2020 | 7/1/2020 | | DONE |
Leon Letson
|
|
|
TEMP see email in docs blh 7-2-2020
|
PubWorks Occupancy Approval | 6/30/2020 | 6/30/2020 | 6/30/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 6/22/2020 | 6/23/2020 | 6/23/2020 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson/ ok pending zoning and others
|
BLD-Final | 6/17/2020 | 6/18/2020 | 6/23/2020 | P | NR |
Tony Young
|
|
|
please call 30 minutes before inspection Phone #: ###-#### Inspection requested via web by bill gullickson
|
FIRE-Final Inspection | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed under kitchen sink in each unit with current inspection tags, knox box is installed by fire sprinkler riser room. Final life fire safety inspection is complete, signature card not available at time of inspection.
please call 30 minutes before inspection Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Energy code compliance | 4/3/2020 | 4/6/2020 | 4/6/2020 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson// ok after fixing a couple areas and fixing fire sprinkler tenting
|
BLD-Framing/Rough-in | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ed Kron// see Bill for the fix list,, minor issues,, ok to insulate
|
BLD-Framing/Rough-in | 3/25/2020 | 3/26/2020 | 3/26/2020 | P | DEFR |
Mike Jordan
|
|
|
please schedule for late afternoon. Thanks Phone #: ###-#### Inspection requested via web by bill gullickson. Due to employee on job site testing poitive for covid-19, inspection can not be performed at this time.
|
BLD-Framing/Rough-in | 3/23/2020 | 3/24/2020 | 3/24/2020 | P | FAIL |
Mike Jordan
|
|
|
Please contact Bill 30 Minutes prior to arrival. Thanks Phone #: ###-#### Inspection requested via web by bill gullickson. Fire caulk all penetrations in 1hr. fire partitions, Install all missed fire blocking, install the dryer vent box per the listing in the 1hr. fire partition. Provide listing for ox boxes in 1hr. fire partition.
|
CHANGE STATUS TO (ISS) | | | 2/19/2020 | | DONE |
|
|
|
plan mod approved
|
BLD-Wall Bracing | 2/14/2020 | 2/18/2020 | 2/18/2020 | A | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####,, exterior ok after minor fixes
|
Plan assigned to (JG) | 2/7/2020 | 2/7/2020 | 2/18/2020 | | PASS |
Javier Guzman
|
|
|
02/18 plan mod Eaglehawk Fourplex - Bldg 5
|
Routing - PLAN CHECK | 2/12/2020 | | 2/18/2020 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 2/18/2020 | | DONE |
|
|
|
**PLAN MOD - DO NOT REISSUE** All plan mod fees assessed on BLD19-02617
|
Routing - MECHANICAL | 2/12/2020 | | 2/12/2020 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 2/7/2020 | | DONE |
|
|
|
plan mod 1
|
BLD-Conference | 1/8/2020 | 1/8/2020 | 1/8/2020 | P | PART |
Tony Young
|
|
|
Pre-Framing Inspection conference. Please call Nic a half hour before arrival. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen// general and rim area fire seperation
|
BLD-Conference | 1/6/2020 | 1/7/2020 | 1/8/2020 | P | DEFR |
Tony Young
|
|
|
Pre-Framing Inspection conference. Please call Nic a half hour before arrival. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Conference | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | DEFR |
Tony Young
|
|
|
Pre-Framing Inspection conference. Please call Nic a half hour before arrival. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Conference | 1/6/2020 | 1/7/2020 | 1/6/2020 | A | CANC |
Tony Young
|
|
|
Pre-Framing Inspection conference. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### >> Inspection requested via web by Nic Van Diepen Inspection cancelled from web by: Nic Van Diepen
|
BLD-Concrete | 12/17/2019 | 12/17/2019 | 12/17/2019 | A | DONE |
Tony Young
|
|
|
Interior slab on grade. Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Energy code compliance | 11/22/2019 | 11/22/2019 | 11/25/2019 | P | PASS |
Tony Young
|
|
|
Foundation rigid Insulation inspection. Thanks! Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Foundation | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Tony Young
|
|
|
Pat- foundation wall inspection Phone #: ###-####// footings ok
|
BLD-Footing | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | NR |
Tony Young
|
|
|
Pat Phone #: ###-####
|
Fees Due Hold | 10/5/2019 | | 11/8/2019 | | DONE |
Brittany Hill
|
|
|
|
Telephone call | | | 10/4/2019 | | DONE |
|
|
|
called Perryman-talked to
Addy in accounting-she will let the GC know that there are more fees due-i told her they wouldn't be able to schedule and inspection untill it was paid
|
Issue PAID IN FULL permit | | | 9/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/19/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/18/2019 | | |
|
|
|
|
Plan assigned to (JG) | 7/17/2019 | 7/18/2019 | 9/18/2019 | | PASS |
Javier Guzman
|
|
|
9/20 3rd rev comp, 08/27 - 506 Eaglehawk Fourplex Bldg 5
|
Routing PW Sewer Design | 9/18/2019 | | 9/18/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 9/18/2019 | | 9/18/2019 | | PASS |
Evan Carpenter
|
|
|
signed off in ePlan by PW Solid Waste Evan Carpenter
|
Routing - PLAN CHECK | 9/16/2019 | | 9/18/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Street Lights | 9/16/2019 | | 9/18/2019 | | PASS |
Tom Marshall
|
|
|
signed off in ePlan by PW Street Lights Tom Marshall
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/18/2019 | | DONE |
|
|
|
Need
ACHD
GC Form
Revised Value
DO NOT ISSUE WITHOUT BLD19-02617-BLD19-02622
|
Routing - Design Review | 9/16/2019 | | 9/17/2019 | | PASS |
Josh Wilson
|
|
|
Revised site and landscape plan ok
|
Routing - PLAN CHECK | 9/3/2019 | | 9/11/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 9/3/2019 | | 9/11/2019 | | PASS |
Troy James
|
|
|
Signed off in ePlan by Troy James
|
Routing Off Site - STRUCTURAL | 9/3/2019 | | 9/11/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by KPFF Engineer
|
Routing PW Drainage | 9/3/2019 | | 9/11/2019 | | PASS |
Melissa Jannusch
|
|
|
Drainage approved under the subdivison review process ODI 3719
|
Routing PW Street Lights | 9/3/2019 | | 9/11/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 9/10/2019 | | 9/11/2019 | | PASS |
Leon Letson
|
|
|
signed off in ePlan Planning Leon Letson
|
Routing - FIRE | 9/3/2019 | 9/3/2019 | 9/10/2019 | | PASS |
Mark Scharfen
|
|
|
09/10-Eaglehawk building 5 resubmittal. Fire review complete. Uploaded rev_fire 09.10.2019.pdf
|
Routing - Design Review | 9/3/2019 | | 9/10/2019 | | FAIL |
Josh Wilson
|
|
|
|
Route to Impact Fee Review | 8/20/2019 | 8/23/2019 | 8/21/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/17/2019 | 7/18/2019 | 8/20/2019 | | FAIL |
Mark Scharfen
|
|
|
08/20 - 506 Eaglehawk Fourplex Bldg 5- review complete. Uploaded rev_fire 08.20.2019.pdf and emailed to architect.
|
Routing Off Site - STRUCTURAL | 7/18/2019 | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by KPFF Engineer
|
Routing PW Street Lights | 7/19/2019 | | 8/20/2019 | | FAIL |
Tom Marshall
|
|
|
Failed in ePlan by PW Street Lights Tom Marshall
|
Routing PW Sewer Design | 7/19/2019 | | 8/20/2019 | | FAIL |
DeAnn Brown
|
|
|
Failed in ePlan by PW Sewer Design DeAnn Brown
|
Routing PW Solid Waste | 7/19/2019 | | 8/20/2019 | | FAIL |
Evan Carpenter
|
|
|
Failed in ePlan by PW Solid Waste Evan Carpenter
|
1st review completed | | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 7/17/2019 | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Drainage | 7/19/2019 | | 7/29/2019 | | FAIL |
Melissa Jannusch
|
|
|
Please provide most recent set of Civil Plan dated 10-1-2018
|
Routing - MECHANICAL | 7/17/2019 | | 7/24/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to Architect
|
Routing - Erosion and Sediment | 7/17/2019 | | 7/23/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid RP, site preparation inspection required.
|
Routing - PLANNING | 7/17/2019 | | 7/21/2019 | | PASS |
Leon Letson
|
|
|
|
Routing - PUBLIC WORKS | 7/17/2019 | | 7/19/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 7/17/2019 | | 7/18/2019 | | FAIL |
Andrea Tuning
|
|
|
Locate the street trees along Bogart Lane within the landscape planter located between the sidewalk and the curb line.
Install landscape planter islands at the terminus of each row of parking. The planters shall be a minimum of 8-feet in width (measured inside of curb to inside of curb) and include the required Class II or Class III tree with low shrubs or other vegetative groundcover.
Install a mixture of deciduous and evergreen trees, shrubs, or other vegetative groundcover in the northwest corner of the site that will create a visual barrier that provides a minimum of 60-percent of a barrier within five years of planting for the existing single-family residential dwelling that is an “out parcel”.
Locate all site lighting outside of the required planter islands.
Clearly identify all mechanical units and how they will be screened.
|
Routing - Addressing | 7/17/2019 | | 7/18/2019 | | PASS |
Doug Chausow
|
|
|
Correct address: 7344 N Lucy Rose Ln
|
Routing - PLUMBING | 7/17/2019 | | 7/18/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Intake Approval | | | 7/17/2019 | | PASS |
Brian McGowan
|
|
|
|
Application received | | | 7/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 15 2019 2:09PM
|