BLD-Final | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Tell Riley
|
|
|
*screened* Ben Phone #: ###-####//final complete per approved plans onisite//no signature card onsite//
|
Permanent Occupancy | | | 5/22/2020 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/18/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Screened-Ben Phone #: ###-####- call for access
|
BLD-Aging Inspection | 3/26/2020 | 3/26/2020 | 3/26/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Energy code compliance | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Tell Riley
|
|
|
bENJAMIN Phone #: ###-####//framing ok//insulation ok//no mechanical needed per Brian//
|
BLD-Framing/Rough-in | 11/5/2019 | 11/6/2019 | 11/6/2019 | A | PART |
Tell Riley
|
|
|
Ben Phone #: ###-####//need mechanical permit and ducting moved where in doorway and partially under wall//ok to fix insulation in vault where existing//call for re-inspection after mechanical//electrical complete//
|
Issue PAID IN FULL permit | | | 10/3/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/22/2019 | 8/25/2019 | 8/23/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 8/23/2019 | | DONE |
|
|
|
NEED ***SIGNATURE ON APP AND SCANNED IN****
ISSUE 19-03003 TO 03005
GC FORM
REVISED VALUE
|
Print Occupancy Form | | | 8/23/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 8/7/2019 | 8/7/2019 | 8/22/2019 | | DONE |
Julie Romig
|
|
|
08/20 - L2 10451 Garverdale Elevation Chiropractic
|
Routing - PLAN CHECK | 8/9/2019 | | 8/22/2019 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 8/22/2019 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/22/2019 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 8/7/2019 | | 8/9/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Addressing | 8/7/2019 | | 8/8/2019 | | PASS |
Doug Chausow
|
|
|
Suite 204
|
Plans ACCEPTED BY PLAN TECH | | | 8/7/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/7/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/7/2019 | | DONE |
|
|
|
|
Application received | | 8/7/2019 | | | |
|
|
|
|