Permit Information
Permit NumberBLD19-03181
StatusIssued
Name C & T CONSTRUCTION
Site Address 7749 W CRESTWOOD DR
Project Name14B.2
Customer NumberBLD19-03180, BLD19-03187-003188
ePlanReviewNo
Description
***02/18/20 PLAN MODIFICATION TO UPDATE 2 HOUR WALL*** (FOUR PERMITS FILED) Permit for the construction of a new 1589 sq. ft., 3 story (first story 189 sq. ft., second story 750 sq. ft. and third story 650 Sq. ft.) Townhouse with 3 bedrooms, 2.5 bathrooms, approximately 45 sq. ft. of covered patio/porch and a 450 sq. ft. attached garage per the approved plans and any notations. C-1D zoning and setbacks per planning. RDP ***SPRINKLERS NOT REQUIRED***LGM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Energy code compliance5/28/20205/28/20205/28/2020APASS
DetailsTell Riley
corrections made//
BLD-Energy code compliance5/27/20205/27/20205/27/2020APART
DetailsTell Riley
Inspection requested via web by Carl Funk//add hangers to area above stairs as discussed//add VB at areas discussed//add truss bracing//add r20 min inuslation in areas r19 was installed//framing that is different than plans is in accordance with engineers site walk though and accepted by him on the first eight units, same framing used on this unit//
BLD-Framing/Rough-in5/22/20205/22/20205/22/2020APART
DetailsTell Riley
Inspection requested via web by Carl Funk//ok to insulate only//add stud for 2nd floor bearing at stairs marked in green//need joist repair//add truss bracing//address head height at stairs//
BLD-Framing/Rough-in5/21/20205/21/20205/21/2020ANR
DetailsTell Riley
Inspection requested via web by Carl Funk//see Joey onsite for corrections list//framing that differs on plans, appears to meet engineers onsite walk through as per the other units//need truss plans on next inspection//also see green marks on plans and in buildings//
BLD-Wall Bracing5/14/20205/14/20205/14/2020PPASS
DetailsTell Riley
Inspection requested via web by Carl Funk//interior shear on fire wall//screws/ nails ok per plans, compliant with engineers email stating blocking is not needed at edges//still need rating for ele heater box in rated wall//
BLD-Wall Bracing5/13/20205/13/20205/13/2020PFAIL
DetailsTell Riley
Firewall Shear Inspection requested via web by Carl Funk//Not ready, not all walls hung, nailing needs to be done at all plates//still need verifiction of ele heater boxes in firewall//
BLD-Wall Bracing5/12/20205/12/20205/12/2020PCANC
DetailsTell Riley
Firewall Shear Inspection requested via web by Carl Funk
BLD-Energy code compliance5/7/20205/8/20205/8/2020APART
DetailsTell Riley
Firewall Insulation Inspection requested via web by Carl Funk//fire separation walls only//per plans//
BLD-Framing/Rough-in5/7/20205/8/20205/8/2020APART
DetailsTell Riley
Firewall blocking Inspection requested via web by Carl Funk//fire separation wall only//Corrections made//need rating information for ele heater box in rated wall(all Units)//
BLD-Framing/Rough-in5/7/20205/7/20205/7/2020AFAIL
DetailsTell Riley
Fire Blocking firewall Inspection requested via web by Carl Funk/framing for fire walls ONLY//add nuts and bolts in areas noted//add studs in areas noted//add fire blocking in areas noted//see details for truss connections at fire walls//complete air seal//
BLD-Energy code compliance5/7/20205/7/20205/7/2020ANR
DetailsTell Riley
Insulation Firewall Inspection requested via web by Carl Funk
BLD-Energy code compliance5/5/20205/5/20205/5/2020ANR
DetailsTell Riley
Firewall insulation Phone #: ###-#### Inspection requested via web by Carl Funk/needs framing inspeciton completed on separation walls prior to insulation//will reschedule when insulation is removed//
Routing - MECHANICAL3/26/2020 3/26/2020 PASS
DetailsTroy James
Resubmitted ACCA report
BLD-Wall Bracing3/19/20203/20/20203/20/2020APART
DetailsTell Riley
Inspection requested via web by Carl Funk
BLD-Wall Bracing3/16/20203/17/20203/17/2020AFAIL
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Carl Funk//need to add nails, fix hold downs nails//did walk through with carl//add hold downs where needed//
OVERRIDE  2/18/2020  
Plan assigned to (RDP)2/11/20202/11/20202/18/2020 DONE
DetailsRob Patrick
02/17 Plan Mod
Routing - PLAN CHECK2/18/2020 2/18/2020 PASS
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  2/18/2020 DONE
DetailsRob Patrick
Permit Ready to Issue  2/18/2020 DONE
**DO NOT REISSUE - PLAN MOD** Fees assessed on BLD19-03180
CHANGE STATUS TO (ISS)  2/18/2020 DONE
plan mod
Plan Modification Accepted  2/11/2020 DONE
2 copies of Sheet A4.4.
BLD-Foundation12/13/201912/13/201912/13/2019PPART
DetailsTell Riley
Gibert Phone #: ###-####//WIP//still need to install hold downs//
BLD-Footing12/10/201912/11/201912/11/2019APASS
DetailsTell Riley
GILBERT Phone #: ###-####//ok per details, site plan and survey pins//
Issue PAID IN FULL permit  11/15/2019 DONE
OVERRIDE  11/14/2019  
Routing - FIRE11/14/201911/14/201911/14/2019 PASS
DetailsLee G Meredith
Sprinklers are not required.
Permit Ready to Issue  11/14/2019 DONE
met
Routing - PLAN CHECK11/14/2019 11/14/2019 PASS
DetailsJenny Nelson
Per RDP Review
Case Summary (BLD)  11/14/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  11/14/2019 DONE
DetailsJenny Nelson
Inspection Record Card- Bld  11/14/2019 DONE
Plan assigned to (RDP)8/20/2019 11/14/2019 DONE
DetailsRob Patrick
09/06 sfd L2 PAPER...09/17 Failed...11/7 Failed
Routing - PLAN CHECK11/7/2019 11/7/2019 FAIL
DetailsRob Patrick
Correction on sheet A4.4
Routing - PLANNING11/1/2019 11/1/2019 PASS
DetailsDavid Moser
Plan resubmittals received  10/25/2019 DONE
Applicant dropped off 2 copies of resubmittal. Sheets: A1.0, A2.1, A2.3, A4.1, S2.1, S2.2A, S2.3A, S2.4A, S2.6, S2.9, S3.0
1st review completed  9/17/2019 FAIL
DetailsRob Patrick
Corrections Req'd
Plan resubmittals received  9/17/2019 DONE
2 large plan- A4.4, S2.1, S2.2, S2.6, S2.7 and S2.8
and 16 RES-Checks
Taken to Rob
Routing - PLAN CHECK8/20/2019 9/17/2019 FAIL
DetailsRob Patrick
Corrections Req'd
Routing - PUBLIC WORKS8/20/2019 9/10/2019 PASS
DetailsAngela Hardy
Plan resubmittals received  8/28/2019 DONE
Two copies each of Landscaping plans stamped and taken to plan reviewer
Routing - MECHANICAL8/20/2019 8/27/2019 PASS
DetailsChad Schwendiman
Routing - PLANNING8/20/2019 8/26/2019 FAIL
DetailsDavid Moser
need to submit a Landscape Plan
Routing - Design Review8/23/2019 8/26/2019 PASS
DetailsKatelyn Menuge
Redlined facade and landscape changes.
Route to Impact Fee Review8/21/20198/24/20198/22/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - Addressing8/20/2019 8/22/2019 PASS
DetailsDoug Chausow
Telephone call  8/20/2019 DONE
Spoke with Carl, he informed me that he is going to submit paper instead of Eplan.
Plans ACCEPTED BY PLAN TECH  8/20/2019 DONE
Recd Pcfee & Taken To Pln CK  8/20/2019 DONE
Intake Approval  8/20/2019 PASS
Application received  8/19/2019 DONE
Application submitted via PDS Online on Aug 19 2019 11:44PM