BLD-Final | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | PASS |
Tell Riley
|
|
|
Chad Phone #: ###-####//ok when fire sprinkler pipes are caulked at penetrations in garage//
|
DOC - Permit Finaled | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Blower Door Test Results | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | DONE |
Tell Riley
|
|
|
4.81 ACH 50
|
BLD-Energy code compliance | 11/14/2019 | 11/15/2019 | 11/15/2019 | P | PASS |
Tell Riley
|
|
|
ryan Phone #: ###-####
|
BLD-Framing/Rough-in | 11/13/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Tell Riley
|
|
|
PJ Phone #: ###-####//corrections made//still need safety glazing--check at final//ok to insulate//
|
BLD-Framing/Rough-in | 11/12/2019 | 11/13/2019 | 11/13/2019 | P | FAIL |
Tell Riley
|
|
|
PJ Phone #: ###-####//need passed sprinkler rough in//fix cut stud//add truss hanger//call for reinspection//
|
BLD-Wall Bracing | 10/31/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Tell Riley
|
|
|
shear // Chad Phone #: ###-####//exterior walls only//
|
BLD-Foundation | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Footing | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Tell Riley
|
|
|
Brain Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/24/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/20/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 8/23/2019 | 8/23/2019 | 9/20/2019 | | DONE |
Jenny Nelson
|
|
|
09/05 sfd L1 Paper. 1st complete 09/05, not showing window on elevation, foundation ventilation, foundation connection detail, shear calcs, specify girder trusses.
|
Routing - PLAN CHECK | 9/20/2019 | | 9/20/2019 | | PASS |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 9/20/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 9/20/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/16/2019 | | DONE |
|
|
|
Two copies of sheets A-2, A-3.A-5, A-8 and 2015 ICR Braced wall calcs. One copy of small plans for sheets submitted stamped and taken to plan reviewer.
|
1st review completed | | | 9/5/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | | | 9/5/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - FIRE | 8/27/2019 | 8/27/2019 | 8/28/2019 | | PASS |
Lee G Meredith
|
|
|
09/05-8759 W Shellie Ln Residential paper LGM
Sprinklers to be provided, as noted on the drawings.
|
Routing - MECHANICAL | 8/26/2019 | | 8/27/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 8/23/2019 | 8/26/2019 | 8/26/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 8/23/2019 | | 8/26/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 8/23/2019 | | 8/23/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/23/2019 | | 8/23/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/23/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/23/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/23/2019 | | PASS |
|
|
|
|
Application received | | 8/23/2019 | | | |
|
|
|
|