Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-03333
StatusIssued
Name ALTECCA LLC
Site Address 350 N MILWAUKEE ST Unit: 1051
Project NameEscape the Room T.I.
Customer NumberDEMO ONLY BLD19-02952
ePlanReviewYes
Description
(ESCAPE THE ROOM - BTS SPACE # 1051) This building is fire sprinkled because it is a mall building. Permit to remodel an 4,342 sqft existing business space in the mall. Work to include: Construct new store front with double main entry doors, non-load bearing interior walls, doors, accessible restroom, finishes, millwork, mechanical work, plumbing work, and electrical work. Approval is contingent on adhering to the approved plans, local codes and ordinances. Interior finishes shall be in compliance with Ch. 8 of the 2015 IBC. This building is fully fire sprinkled. Any alterations or modifications to the buildings fire sprinkler or fire alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise fire department. The smoke evacuation system shall remain operational as originally installed under the 1985 UBC. NOTE: a separate sign permit for interior mall signage is required before sign installation. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/12/20203/13/20203/13/2020PPEND
DetailsMike Jordan
Taylor Phone #: ###-####. Needs test data for PVC ceiling tile.
FIRE-Final Inspection3/12/20203/13/20203/13/2020APASS
DetailsTroy Cobbley
Life safety passed. Taylor Phone #: ###-####
FIRE-Conference2/18/20202/19/20202/19/2020ADONE
DetailsTroy Cobbley
Conference was over the door hardware for the escape rooms. The hardware operation needs to meet Chapter 10 of the fire and building codes. It appears that sections 1010.1.9.8 and 1010.1.9.9 would be the applicable code sections. Also a fire alarm permit is required for the fire alarm interconnect required per the drawings and IFC section 1010.1.9.8. Also the project related fire sprinkler permit needs finaled.

Taylor Phone #: ###-####
BLD-Final2/14/20202/18/20202/18/2020PNR
DetailsMike Jordan
call for access- Taylor Phone #: ###-####
FIRE-Final Inspection2/14/20202/18/20202/18/2020ACANC
DetailsTroy Cobbley
Need the project related fire sprinkler permit addressed and a separate FIR permit is needed for the alarm work.

call for access- Taylor Phone #: ###-####
BLD-Ceiling Grid Inspection1/8/20201/8/20201/8/2020PPASS
DetailsMike Jordan
Taylor Phone #: ###-####
BLD-Ceiling Grid Inspection1/7/20201/8/20201/8/2020AFAIL
DetailsMike Jordan
Taylor Phone #: ###-####
BLD-Framing/Rough-in11/12/201911/13/201911/13/2019APASS
DetailsBrandon Shaw
Bathroom walls, ok to cover pending trades aprroval...
All other areas, ok to cover...
BLD-Framing/Rough-in11/7/201911/8/201911/7/2019ACANC
DetailsMike Jordan
Escape Rooms Phone #: ###-#### >> Inspection requested via web by Blake Neeser Inspection cancelled from web by: Blake Neeser
Issue PAID IN FULL permit  10/10/2019 DONE
Print Occupancy Form  10/10/2019 DONE
Routing - PLAN CHECK10/9/2019 10/9/2019 PASS
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  10/9/2019 DONE
DetailsMichael Hanson
Permit Ready to Issue  10/9/2019 DONE
ALL MET
Need GC
Need rev cert of val
Plan assigned to (M_H)9/5/2019 10/9/2019 DONE
DetailsMichael Hanson
1st review completed - 10/02 #520 L3 ePlan - Escape The Room - BTS #1051
Route to Impact Fee Review10/2/201910/5/201910/3/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - PLAN CHECK9/5/2019 10/2/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required.
1st review completed  10/2/2019 FAIL
DetailsMichael Hanson
Routing - FIRE9/5/20199/5/20199/30/2019 PASS
DetailsMark Stumbaugh
10/02-BTS #1051 Escape the Room TI 520
Telephone call  9/24/2019 DONE
cusotmer called wanting conference inspeciton-told him the permit had to be issued before we could schedule and inspection
Routing - MECHANICAL9/5/2019 9/10/2019 PASS
DetailsTroy James
Routing - PLUMBING9/5/2019 9/6/2019 PASS
DetailsDan Ediger
Per plans and ISPC
Routing - Addressing9/5/2019 9/6/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS9/5/2019 9/6/2019 PASS
DetailsAngela Hardy
Intake Approval  9/5/2019 PASS
DetailsJavier Guzman
Prescreen approved by JG.
Intake Approval  8/30/2019 FAIL
DetailsJavier Guzman
The ComCheck was not found on plan sheet E3.0 as noted on checklist
Intake Approval  8/29/2019 FAIL
DetailsJavier Guzman
This is a assembly change in use project provide and upload a completed 520 application and 520 checklist with any additional items requested from the checklist
Application received  8/28/2019 DONE
Application submitted via PDS Online on Aug 28 2019 2:53PM